195 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) 1 high risk | 195 | 20 | ₹11.89 Cr | 55 | 29.1 | NEELAM YOGESH JAISWAL 14% of spend · 29 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Prashant Yadaorao Padole BHANDARA-GONDIYA | 73 | ₹5.38 Cr | 18 |
| Kirsan Namdeo GADCHIROLI-CHIMUR | 62 | ₹3.03 Cr | 6 |
| Praful Patel Sitting Rajya Sabha | 60 | ₹3.48 Cr | 31 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 105 | ₹7.38 Cr | 20 |
| Roads & Paving | 30 | ₹1.49 Cr | 11 |
| Water | 16 | ₹32.08 L | 5 |
| Education | 16 | ₹1.14 Cr | 5 |
| Religious & Cultural | 13 | ₹77.40 L | 8 |
| Other | 4 | ₹25.00 L | 3 |
| Equipment & Vehicles | 3 | ₹6.00 L | 0 |
| Street Lighting | 3 | ₹14.13 L | 1 |
| Drainage & Sanitation | 3 | ₹18.46 L | 1 |
| Boundary & Protection | 1 | ₹9.93 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Sabha Mandap ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in GONDIA (100% above, 29 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 169 d | +100% | 74.3 | HIGH |
| LAKHEGAON ME BHARAT TUMSARE KE NIWAS SE LAKHARAM RAHANGDALE ₹1,000,000 against a ₹500,000 median for Roads & Paving works in GONDIA (100% above, 79 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 99 d | +100% | 64.6 | MEDIUM |
| Gram Navegaon Dhapewada me Bajar Chauk me Sabhamandap Bandhk ₹1,000,000 against a ₹700,000 median for Community Buildings works in GONDIA (43% above, 136 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 408 d | +43% | 63.0 | MEDIUM |
| Fulchur, Ta. Dist. Gondia me ward no. 2 me samaj kalyan bhaw ₹1,000,000 against a ₹700,000 median for Community Buildings works in GONDIA (43% above, 136 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 364 d | +43% | 62.8 | MEDIUM |
| Gram Kakodi, Ta. Deori, Dist. Gondia me Kabir Kuti Zariya Pa Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹7.00 L | 371 d | 0% | 61.6 | MEDIUM |
| Tiroda City me Railway Station Road par Shri Gajanan Maharaj 408 days beyond expected completion | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹1.30 L | 408 d | -74% | 60.3 | MEDIUM |
| Gram Pathari me Bhojraj Gaundharya ke niwas ke pas 1 borewel 409 days beyond expected completion | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹1.30 L | 409 d | -7% | 60.3 | MEDIUM |
| Gram Menghatola me Surendra Waghmare ke niwas ke pas 1 borew 409 days beyond expected completion | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹1.30 L | 409 d | -7% | 60.3 | MEDIUM |
| Construction of Community Hall ₹1,000,000 against a ₹700,000 median for Community Buildings works in GONDIA (43% above, 136 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 169 d | +43% | 60.0 | MEDIUM |
| Construction of Community Hall ₹1,000,000 against a ₹700,000 median for Community Buildings works in GONDIA (43% above, 136 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 169 d | +43% | 60.0 | MEDIUM |
| Construction of Community Hall ₹1,000,000 against a ₹700,000 median for Community Buildings works in GONDIA (43% above, 136 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 169 d | +43% | 60.0 | MEDIUM |
| Construction of Community Hall ₹1,000,000 against a ₹700,000 median for Community Buildings works in GONDIA (43% above, 136 peer works) | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹10.00 L | 169 d | +43% | 60.0 | MEDIUM |
| Gram Sejgaon, Ta. Tiroda, Dist. Gondia me Maa Gaytri Mandir 409 days beyond expected completion | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹5.00 L | 409 d | 0% | 59.8 | MEDIUM |
| Gram Fulchur, Ta. Dist. Gondia me RTO Office ke pass Shubhla 345 days beyond expected completion | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹5.00 L | 345 d | 0% | 59.6 | MEDIUM |
| Gram Kamtha, Ta. Dist. Gondia me Rajesh Mohare ke Dhaba se R 329 days beyond expected completion | GONDIA(DISTRICT COLLECTOR GONDIA_IDA) | Recommended | ₹5.00 L | 329 d | 0% | 59.3 | MEDIUM |