Open this link on a larger screen to see the verification queue.
171 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | 171 | 158 | ₹9.33 Cr | 7 | 16.1 | Kancheshwar Majur Sahakari Sanstha Maryadit 6% of spend · 88 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Omprakash Bhupalsinh Alias Pavan Rajenimbalkar OSMANABAD | 170 | ₹9.26 Cr | 7 |
| Ashokrao Shankarrao Chavan Sitting Rajya Sabha | 1 | ₹7.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 77 | ₹4.30 Cr | 2 |
| Community Buildings | 40 | ₹2.66 Cr | 0 |
| Water | 23 | ₹66.59 L | 4 |
| Street Lighting | 12 | ₹55.23 L | 0 |
| Sports | 8 | ₹54.96 L | 0 |
| Education | 5 | ₹29.85 L | 1 |
| Equipment & Vehicles | 2 | ₹6.00 L | 0 |
| Drainage & Sanitation | 2 | ₹9.96 L | 0 |
| Religious & Cultural | 1 | ₹6.82 L | 0 |
| Boundary & Protection | 1 | ₹6.94 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of rooms and halls in school and colleges at Up ₹1,499,700 against a ₹325,000 median for Education works in DHARASHIV (361% above, 10 peer works) | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹15.00 L | 547 d | +361% | 52.4 | MEDIUM |
| Construction of cement road ₹995,598 against a ₹500,000 median for Roads & Paving works in DHARASHIV (99% above, 114 peer works) | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Completed | ₹9.96 L | — | +99% | 47.2 | MEDIUM |
| Installation of Borewells and Motor at Korbu Galli Ter Tahs Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹74,999 | 926 d | -75% | 43.1 | MEDIUM |
| Installation of Borewells and Motor at Jay Malhar Chauk Bus Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹1.02 L | 926 d | -66% | 43.1 | MEDIUM |
| Construction of cement Concrete Road towards Muslim communit Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹96,150 | 926 d | -81% | 43.1 | MEDIUM |
| Installation Borewells and Motor at Shikat Galli Ter Tahsil Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹1.06 L | 926 d | -65% | 43.0 | MEDIUM |
| Installation of Borewells and Pipelines at Kondjigad Tahsil Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹3.00 L | 1,086 d | -0% | 42.9 | MEDIUM |
| Installing community drinking water plants ₹499,247 against a ₹299,842 median for Water works in DHARASHIV (66% above, 36 peer works) | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Completed | ₹4.99 L | — | +67% | 39.1 | LOW |
| Paver blocks at Bhimnagar Toramba block Lohara 548 days beyond expected completion | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹5.00 L | 548 d | 0% | 35.8 | LOW |
| construction of community hall at wagholi block kalamb dist 548 days beyond expected completion | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹5.00 L | 548 d | -29% | 35.8 | LOW |
| Installing borewell at shivkarvadi 547 days beyond expected completion | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹2.00 L | 547 d | -33% | 35.3 | LOW |
| Purchase of smart boards, visual display units and projector 547 days beyond expected completion | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹3.00 L | 547 d | 0% | 35.3 | LOW |
| Purchase of IT systems, including hardware and software for 547 days beyond expected completion | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹3.00 L | 547 d | 0% | 35.3 | LOW |
| Installation of borewell and motor water pipelines 547 days beyond expected completion | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Recommended | ₹3.00 L | 547 d | +0% | 35.3 | LOW |
| Construction of roads work Completed work has no photographic documentation on record | Dharashiv(DISTRICT COLLECTOR OSMANABAD_IDA) | Completed | ₹6.42 L | — | +28% | 34.0 | LOW |