79 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | 79 | 32 | ₹6.72 Cr | 11 | 27.3 | Alok Electricals Bhandara 18% of spend · 55 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Praful Patel Sitting Rajya Sabha | 40 | ₹2.78 Cr | 8 |
| Sunil Baburao Mendhe BHANDARA-GONDIYA | 38 | ₹3.70 Cr | 2 |
| Imran Pratapgarhi Sitting Rajya Sabha | 1 | ₹25.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 31 | ₹2.17 Cr | 1 |
| Community Buildings | 14 | ₹1.11 Cr | 1 |
| Water | 9 | ₹15.75 L | 3 |
| Education | 7 | ₹21.97 L | 1 |
| Drainage & Sanitation | 7 | ₹42.30 L | 1 |
| Religious & Cultural | 6 | ₹35.41 L | 2 |
| Sports | 3 | ₹2.10 Cr | 1 |
| Equipment & Vehicles | 2 | ₹19.45 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| senior citizens multipurpose association bhandara city me Sh ₹1,800,000 against a ₹1,000,000 median for Equipment & Vehicles works in BHANDARA (80% above, 18 peer works) | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹18.00 L | 162 d | +80% | 66.7 | MEDIUM |
| Gram Mokhara, Ta. Pauni, Dist. Bhandara me Hanuman Mandir Pa 355 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹5.00 L | 355 d | 0% | 57.8 | MEDIUM |
| jaitpur me hukare mohalle me shri pundlik shende ke niwas ke 191 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.50 L | 191 d | 0% | 56.2 | MEDIUM |
| tawasi me bus stand ke pass 1 borwell 191 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.50 L | 191 d | 0% | 56.2 | MEDIUM |
| tawasi me shri dadaram sonwane ke niwas ke pass 1 borewell 191 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.50 L | 191 d | 0% | 56.2 | MEDIUM |
| At. Mohadi Th Mohadi Development of playfields and sports gr Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹2.00 Cr | 555 d | 0% | 52.6 | MEDIUM |
| Construction of Anganwadi building at Jamani tah dist Bhanda ₹500,000 against a ₹274,902 median for Education works in BHANDARA (82% above, 8 peer works) | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹5.00 L | 568 d | +82% | 49.6 | MEDIUM |
| Khamari Buti me Hanuman Mandir ke pass paving block Nirman K ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in BHANDARA (100% above, 12 peer works) | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹10.00 L | — | +100% | 49.1 | MEDIUM |
| Lobhi me anjana deshmukh se bandu parteki ke ghar tak cement ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in BHANDARA (100% above, 13 peer works) | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹10.00 L | — | +100% | 49.1 | MEDIUM |
| Construction of Cultural Center near Kohali Samaj Bhawan ₹2,500,000 against a ₹1,000,000 median for Community Buildings works in BHANDARA (150% above, 67 peer works) | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹25.00 L | — | +150% | 49.1 | MEDIUM |
| DIGHORI MOTHI ME Ramesh Chunne se Nandu Karanjekar ke khet t 98 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹5.00 L | 98 d | -28% | 43.4 | MEDIUM |
| Construction of community hall near hanuman mandir at Rohana 568 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹6.00 L | 568 d | -40% | 38.9 | LOW |
| Construction of borewell near sai mandir in ward no.16 at NP 568 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.00 L | 568 d | -33% | 37.6 | LOW |
| Construction of borewell near Shivaji statue in ward no.6 at 568 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.00 L | 568 d | -33% | 37.6 | LOW |
| Construction of borewell near Jyoti Gymnasium in ward no.6 a 568 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.00 L | 568 d | -33% | 37.6 | LOW |