120 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | 120 | 14 | ₹11.14 Cr | 42 | 34.9 | SAURABH WASUDEO CHARDE 12% of spend · 23 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Prashant Yadaorao Padole BHANDARA-GONDIYA | 79 | ₹8.11 Cr | 33 |
| Praful Patel Sitting Rajya Sabha | 40 | ₹2.78 Cr | 8 |
| Imran Pratapgarhi Sitting Rajya Sabha | 1 | ₹25.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 53 | ₹6.22 Cr | 19 |
| Roads & Paving | 33 | ₹2.31 Cr | 5 |
| Equipment & Vehicles | 16 | ₹1.62 Cr | 12 |
| Religious & Cultural | 6 | ₹35.50 L | 2 |
| Drainage & Sanitation | 6 | ₹37.00 L | 1 |
| Water | 3 | ₹4.50 L | 3 |
| Boundary & Protection | 2 | ₹11.95 L | 0 |
| Education | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| senior citizens multipurpose association bhandara city me Sh ₹1,800,000 against a ₹1,000,000 median for Equipment & Vehicles works in BHANDARA (80% above, 18 peer works) | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹18.00 L | 162 d | +80% | 66.7 | MEDIUM |
| Gram Mokhara, Ta. Pauni, Dist. Bhandara me Hanuman Mandir Pa 355 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹5.00 L | 355 d | 0% | 57.8 | MEDIUM |
| Construction of Hall 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹10.00 L | 170 d | 0% | 56.8 | MEDIUM |
| jaitpur me hukare mohalle me shri pundlik shende ke niwas ke 191 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.50 L | 191 d | 0% | 56.2 | MEDIUM |
| tawasi me bus stand ke pass 1 borwell 191 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.50 L | 191 d | 0% | 56.2 | MEDIUM |
| tawasi me shri dadaram sonwane ke niwas ke pass 1 borewell 191 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹1.50 L | 191 d | 0% | 56.2 | MEDIUM |
| Construction of Hall 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | -30% | 56.0 | MEDIUM |
| Construction of cement concrete road 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | +1% | 56.0 | MEDIUM |
| Construction of Hall 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | -30% | 56.0 | MEDIUM |
| Construction of Hall 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | -30% | 56.0 | MEDIUM |
| Construction of cement road 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | +1% | 56.0 | MEDIUM |
| Construction of cement road 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | +1% | 56.0 | MEDIUM |
| Construction of Hall 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | -30% | 56.0 | MEDIUM |
| Construction of Hall 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | -30% | 56.0 | MEDIUM |
| Construction of Hall 170 days beyond expected completion | BHANDARA(DISTRICT COLLECTOR BHANDARA_IDA) | Recommended | ₹7.00 L | 170 d | -30% | 56.0 | MEDIUM |