108 works across 1 implementing agency, recommended by 6 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | VIDISHA(District Collector Vidisha_IDA) 5 high risk | 108 | 26 | ₹6.81 Cr | 18 | 23.4 | MP STATE AGRO VIDISHA 20% of spend · 54 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Lata Wankhede SAGAR | 75 | ₹4.92 Cr | 0 |
| Shivraj Singh Chouhan VIDISHA | 26 | ₹1.36 Cr | 12 |
| Vivek K. Tankha Sitting Rajya Sabha | 3 | ₹15.00 L | 2 |
| Maya Naroliya Sitting Rajya Sabha | 2 | ₹17.00 L | 2 |
| L. Murugan Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
| Kavita Patidar Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 71 | ₹3.92 Cr | 8 |
| Community Buildings | 17 | ₹1.09 Cr | 6 |
| Other | 8 | ₹49.48 L | 4 |
| Education | 4 | ₹37.36 L | 0 |
| Religious & Cultural | 3 | ₹24.34 L | 0 |
| Street Lighting | 3 | ₹53.38 L | 0 |
| Sports | 1 | ₹9.34 L | 0 |
| Water | 1 | ₹5.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Gram Nenwas kalan main Gopal singh ke ghar se school ki aur ₹1,000,000 against a ₹500,000 median for Roads & Paving works in VIDISHA (100% above, 164 peer works) | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹10.00 L | 237 d | +100% | 74.6 | HIGH |
| CC Road from NABARD road to Karondiya connecting road in GP ₹1,000,000 against a ₹500,000 median for Roads & Paving works in VIDISHA (100% above, 164 peer works) | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹10.00 L | 173 d | +100% | 73.7 | HIGH |
| community building ₹1,800,000 against a ₹500,000 median for Community Buildings works in VIDISHA (260% above, 46 peer works) | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹18.00 L | 166 d | +260% | 72.7 | HIGH |
| community building ₹1,800,000 against a ₹500,000 median for Community Buildings works in VIDISHA (260% above, 46 peer works) | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹18.00 L | 166 d | +260% | 72.7 | HIGH |
| community building ₹1,800,000 against a ₹500,000 median for Community Buildings works in VIDISHA (260% above, 46 peer works) | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹18.00 L | 166 d | +260% | 72.7 | HIGH |
| Gram Dhobi Kheda, Gram Panchayat Dhobi Kheda, Janpad Panchay 310 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹7.00 L | 310 d | +40% | 59.6 | MEDIUM |
| Gram Dhobi Kheda, Gram Panchayat Dhobi Kheda, Janpad Panchay 292 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹5.00 L | 292 d | 0% | 57.7 | MEDIUM |
| construction on manglik bhawan near hanuman mandir ₹1,000,000 against a ₹500,000 median for Community Buildings works in VIDISHA (100% above, 46 peer works) | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹10.00 L | 57 d | +100% | 57.5 | MEDIUM |
| Gram Newli me Malaniya road se kheto ki aur sampark sadak ni 159 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹7.00 L | 159 d | +40% | 56.7 | MEDIUM |
| chabutra 166 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹50,000 | 166 d | -90% | 56.3 | MEDIUM |
| chabutra 166 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹1.00 L | 166 d | -80% | 55.4 | MEDIUM |
| cc road 166 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹3.00 L | 166 d | -40% | 53.9 | MEDIUM |
| cycle stand 166 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹2.00 L | 166 d | -60% | 53.8 | MEDIUM |
| cycle stand 166 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹2.00 L | 166 d | -60% | 53.8 | MEDIUM |
| cycle stand 166 days beyond expected completion | VIDISHA(District Collector Vidisha_IDA) | Recommended | ₹2.00 L | 166 d | -60% | 53.8 | MEDIUM |