13 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | 13 | 8 | ₹1.86 Cr | 5 | 36.4 | DHS SEPARATE BANK ACCOUT ASHOK NAGAR 22% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Jyotiraditya M Scindia GUNA | 13 | ₹1.86 Cr | 5 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 9 | ₹1.10 Cr | 3 |
| Health | 2 | ₹50.00 L | 2 |
| Community Buildings | 1 | ₹10.00 L | 0 |
| Education | 1 | ₹16.08 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Purchase of Ambulance Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Recommended | ₹32.00 L | 240 d | 0% | 67.8 | MEDIUM |
| Purchase of Ambulance Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Recommended | ₹18.00 L | 239 d | 0% | 64.8 | MEDIUM |
| CC road construction Completed work has no photographic documentation on record | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹29.98 L | — | +200% | 54.9 | MEDIUM |
| CC road construction 119 days beyond expected completion | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Recommended | ₹10.00 L | 119 d | 0% | 50.2 | MEDIUM |
| CC Road Construction in Village Ratbhanpur Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Recommended | ₹10.00 L | 325 d | 0% | 42.1 | MEDIUM |
| CC Road Construction Completed work has no photographic documentation on record | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹10.00 L | — | 0% | 34.8 | LOW |
| Construction of CC Road 100% similarity with another nearby work | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹10.00 L | — | -0% | 30.4 | LOW |
| Construction of CC Road 100% similarity with another nearby work | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹10.00 L | — | 0% | 30.3 | LOW |
| CC road construction 100% similarity with another nearby work | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹9.99 L | — | -0% | 30.3 | LOW |
| Construction of community hall 119 days beyond expected completion | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Recommended | ₹10.00 L | 119 d | 0% | 30.2 | LOW |
| Improvement of electricity in Law College, Marup, Ashoknagar Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹16.08 L | — | 0% | 17.4 | LOW |
| Construction of Pavers and Boundary wall in School premises | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹9.99 L | — | -0% | 10.3 | LOW |
| Construction of Community Hall and CC Road in Village Chakk | ASHOKNAGAR(DISTRICT COLLECTOR ASHOKNAGAR_IDA) | Completed | ₹9.98 L | — | -0% | 10.2 | LOW |