182 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | 182 | 68 | ₹10.50 Cr | 12 | 21.3 | KRIDL BHUSIRI ACCOUNT WORKS 28% of spend · 44 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| K Rajashekar Basavaraj Hitnal KOPPAL | 180 | ₹9.76 Cr | 10 |
| Nirmala Sitharaman Sitting Rajya Sabha | 1 | ₹48.86 L | 1 |
| Dharmasthala Veerendra Heggade Nominated Rajya Sabha | 1 | ₹25.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 52 | ₹3.10 Cr | 3 |
| Community Buildings | 43 | ₹2.53 Cr | 7 |
| Street Lighting | 22 | ₹1.35 Cr | 0 |
| Education | 22 | ₹1.10 Cr | 0 |
| Equipment & Vehicles | 17 | ₹56.00 L | 0 |
| Water | 9 | ₹44.95 L | 2 |
| Sports | 8 | ₹77.93 L | 0 |
| Drainage & Sanitation | 3 | ₹19.97 L | 0 |
| Religious & Cultural | 2 | ₹13.00 L | 0 |
| Health | 2 | ₹9.97 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Continued Santa Kanakadasa Community Hall in ₹2,500,000 against a ₹300,000 median for Community Buildings works in KOPPAL (733% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹25.00 L | 288 d | +733% | 55.0 | MEDIUM |
| Construction of community hall in ward nm 17 of kushtagi tow ₹1,000,000 against a ₹300,000 median for Community Buildings works in KOPPAL (233% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹10.00 L | 171 d | +233% | 53.7 | MEDIUM |
| Drilling of borewll and installation of motor and laying of 194 days beyond expected completion | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹5.00 L | 194 d | 0% | 50.5 | MEDIUM |
| Drilling of borewll and installation of motor and laying of 194 days beyond expected completion | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹5.00 L | 194 d | 0% | 50.5 | MEDIUM |
| To execute the construction work of the Rotary Seva Bhavan b ₹2,500,000 against a ₹396,446 median for Roads & Paving works in KOPPAL (531% above, 143 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹25.00 L | — | +531% | 50.0 | MEDIUM |
| Setting up of Farmers Training Center and Common Facility Ce ₹4,886,000 against a ₹300,000 median for Community Buildings works in KOPPAL (1529% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Completed | ₹48.86 L | — | +1529% | 50.0 | MEDIUM |
| Construction of community hall (Kanaka Bhavana) at baadimana ₹500,000 against a ₹300,000 median for Community Buildings works in KOPPAL (67% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹5.00 L | 192 d | +67% | 46.7 | MEDIUM |
| Construction of continued shadi mahal community hall in kush ₹500,000 against a ₹300,000 median for Community Buildings works in KOPPAL (67% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹5.00 L | 178 d | +67% | 46.4 | MEDIUM |
| Construction of CC Road in Achalapur village of koppal taalu ₹1,000,000 against a ₹396,446 median for Roads & Paving works in KOPPAL (152% above, 143 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹10.00 L | — | +152% | 42.9 | MEDIUM |
| Construction of CC Road in Achalapur Tanda of koppal taaluk ₹1,000,000 against a ₹396,446 median for Roads & Paving works in KOPPAL (152% above, 143 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹10.00 L | — | +152% | 42.9 | MEDIUM |
| Construction of community hall in Ghattreddihal village unde ₹500,000 against a ₹300,000 median for Community Buildings works in KOPPAL (67% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹5.00 L | 147 d | +67% | 42.1 | MEDIUM |
| Construction of community hall at vakkandurga village of kus ₹500,000 against a ₹300,000 median for Community Buildings works in KOPPAL (67% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹5.00 L | 147 d | +67% | 42.1 | MEDIUM |
| Construction of cold storage in Koppal taluk farm growers sa 194 days beyond expected completion | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹10.00 L | 194 d | 0% | 39.3 | LOW |
| Construction of continued community hall in kaalidas nagar o ₹500,000 against a ₹300,000 median for Community Buildings works in KOPPAL (67% above, 116 peer works) | KOPPAL(DEPUTY COMMISSIONER KOPPAL_IDA) | Recommended | ₹5.00 L | 126 d | +67% | 39.2 | LOW |