350 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | 350 | 83 | ₹16.89 Cr | 124 | 28.4 | BLUESKART ECOMMERCE PRIVATE LIMITED 17% of spend · 64 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Captain Brijesh Chowta DAKSHINA KANNADA | 206 | ₹9.51 Cr | 0 |
| Dharmasthala Veerendra Heggade Nominated Rajya Sabha | 139 | ₹6.73 Cr | 119 |
| Nirmala Sitharaman Sitting Rajya Sabha | 2 | ₹25.00 L | 2 |
| Lahar Singh Siroya Sitting Rajya Sabha | 2 | ₹35.00 L | 2 |
| Jaggesh Sitting Rajya Sabha | 1 | ₹5.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 141 | ₹8.29 Cr | 6 |
| Education | 135 | ₹2.89 Cr | 112 |
| Religious & Cultural | 21 | ₹1.06 Cr | 0 |
| Community Buildings | 18 | ₹97.97 L | 0 |
| Boundary & Protection | 12 | ₹2.05 Cr | 4 |
| Drainage & Sanitation | 10 | ₹1.21 Cr | 2 |
| Street Lighting | 5 | ₹7.30 L | 0 |
| Sports | 4 | ₹17.20 L | 0 |
| Other | 2 | ₹9.92 L | 0 |
| Health | 1 | ₹3.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of community hall at Saraswathi School, Hanuman ₹1,000,000 against a ₹145,000 median for Education works in DAKSHINA KANNADA (590% above, 274 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹10.00 L | 105 d | +590% | 65.7 | MEDIUM |
| Construction of class rooms at Sri Rama school, Sulkeri, Bel ₹2,500,000 against a ₹145,000 median for Education works in DAKSHINA KANNADA (1624% above, 274 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹25.00 L | 105 d | +1624% | 65.7 | MEDIUM |
| Construction of classrooms at Vivekananda Training Centre ₹1,500,000 against a ₹145,000 median for Education works in DAKSHINA KANNADA (934% above, 274 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹15.00 L | 94 d | +934% | 64.2 | MEDIUM |
| Construction of a 25x8 concrete retaining wall for the Ashok ₹7,650,000 against a ₹750,000 median for Boundary & Protection works in DAKSHINA KANNADA (920% above, 24 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹76.50 L | 64 d | +920% | 60.0 | MEDIUM |
| Construction of a 5x8 concrete retaining wall for the Ashoka ₹1,900,000 against a ₹750,000 median for Boundary & Protection works in DAKSHINA KANNADA (153% above, 24 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹19.00 L | 64 d | +153% | 60.0 | MEDIUM |
| Construction of a 300-meter-long concrete drain with a slab ₹2,750,000 against a ₹750,000 median for Drainage & Sanitation works in DAKSHINA KANNADA (267% above, 20 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹27.50 L | 64 d | +267% | 60.0 | MEDIUM |
| Construction of a 600 meter long concrete drain without a sl ₹5,000,000 against a ₹750,000 median for Drainage & Sanitation works in DAKSHINA KANNADA (567% above, 20 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹50.00 L | 64 d | +567% | 60.0 | MEDIUM |
| Construction of a 25x7 (length x height) concrete retaining ₹5,000,000 against a ₹750,000 median for Boundary & Protection works in DAKSHINA KANNADA (567% above, 24 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹50.00 L | 64 d | +567% | 60.0 | MEDIUM |
| Construction of a 15x5 (length x height) concrete retaining ₹1,800,000 against a ₹750,000 median for Boundary & Protection works in DAKSHINA KANNADA (140% above, 24 peer works) | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹18.00 L | 64 d | +140% | 60.0 | MEDIUM |
| Providing Smart Class Unit (1 Nos) To Govt. Upgraded Primary 223 days beyond expected completion | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹1.45 L | 223 d | 0% | 58.7 | MEDIUM |
| PROVIDING SMART CLASS UNIT (1 Nos) to GOVT. UPGRADED PRIMAR 223 days beyond expected completion | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹1.45 L | 223 d | 0% | 58.7 | MEDIUM |
| PROVIDING SMART CLASS UNIT (1 Nos) to GOVT. UPGRADED PRIMAR 223 days beyond expected completion | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹1.45 L | 223 d | 0% | 58.7 | MEDIUM |
| PROVIDING SMART CLASS UNIT (1 Nos) to GOVT. UPGRADED PRIMAR 223 days beyond expected completion | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹1.45 L | 223 d | 0% | 58.7 | MEDIUM |
| PROVIDING SMART CLASS UNIT (1 Nos) to GOVT. HIGHER PRIMARY 223 days beyond expected completion | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹1.45 L | 223 d | 0% | 58.7 | MEDIUM |
| PROVIDING SMART CLASS UNIT (1 Nos) to GOVT. HIGHER PRIMARY 223 days beyond expected completion | DAKSHINA KANNADA(DEPUTY COMMISSIONER DAKSHIN KANNAD MANGALORE_IDA) | Recommended | ₹1.45 L | 223 d | 0% | 58.7 | MEDIUM |