191 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | 191 | 9 | ₹10.22 Cr | 22 | 24.3 | Project Director Nirmithi Kendra Chitradrga 52% of spend · 27 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Govind Makthappa Karjol CHITRADURGA | 188 | ₹9.87 Cr | 19 |
| G.C. Chandrashekhar Sitting Rajya Sabha | 2 | ₹9.80 L | 2 |
| Lahar Singh Siroya Sitting Rajya Sabha | 1 | ₹25.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 89 | ₹4.75 Cr | 4 |
| Education | 50 | ₹2.59 Cr | 6 |
| Religious & Cultural | 21 | ₹96.99 L | 4 |
| Drainage & Sanitation | 10 | ₹52.00 L | 1 |
| Boundary & Protection | 5 | ₹19.87 L | 0 |
| Roads & Paving | 5 | ₹22.30 L | 2 |
| Water | 5 | ₹37.00 L | 1 |
| Health | 3 | ₹14.00 L | 2 |
| Equipment & Vehicles | 1 | ₹25.00 L | 1 |
| Street Lighting | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| construction of bridge near chitradurga district, challakere 261 days beyond expected completion | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹4.90 L | 261 d | 0% | 62.0 | MEDIUM |
| construction of roads from talakunayakanahatti to obayanahat 261 days beyond expected completion | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹4.90 L | 261 d | 0% | 62.0 | MEDIUM |
| Construction of Class room to Government Higher Primary Boys ₹1,000,000 against a ₹400,000 median for Education works in CHITRADURGA (150% above, 54 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 191 d | +150% | 58.9 | MEDIUM |
| Continuation work of Community hall to Karnataka State Gover ₹1,000,000 against a ₹500,000 median for Community Buildings works in CHITRADURGA (100% above, 153 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 206 d | +100% | 58.9 | MEDIUM |
| Construction of School Room to Government Higher Primary Sch ₹1,000,000 against a ₹400,000 median for Education works in CHITRADURGA (150% above, 54 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 167 d | +150% | 57.1 | MEDIUM |
| Construction of Public Bathroom near Siddeshwara swamy templ ₹800,000 against a ₹400,000 median for Religious & Cultural works in CHITRADURGA (100% above, 21 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹8.00 L | 157 d | +100% | 55.7 | MEDIUM |
| Construction of New Hostel building in Hosyelanadu village, ₹2,500,000 against a ₹400,000 median for Education works in CHITRADURGA (525% above, 54 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹25.00 L | — | +525% | 53.9 | MEDIUM |
| Construction of School room for Prashanti Vidyalaya School u ₹1,000,000 against a ₹400,000 median for Education works in CHITRADURGA (150% above, 54 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 141 d | +150% | 53.5 | MEDIUM |
| Construction of Room building with furniture in the Premises Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹25.00 L | 290 d | 0% | 49.9 | MEDIUM |
| Construction of Toilet Block to Women Nursing College of Bap ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in CHITRADURGA (100% above, 11 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 72 d | +100% | 43.9 | MEDIUM |
| Continuation work of Construction of Rangamandira at Hariyab ₹1,000,000 against a ₹400,000 median for Religious & Cultural works in CHITRADURGA (150% above, 21 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 72 d | +150% | 43.9 | MEDIUM |
| Construction of School room to Government Higher Primary Sch ₹1,000,000 against a ₹400,000 median for Education works in CHITRADURGA (150% above, 54 peer works) | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 72 d | +150% | 43.9 | MEDIUM |
| Continuation of work of Goshale(Cowshed) at Roppa village of 202 days beyond expected completion | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹10.00 L | 202 d | 0% | 43.7 | MEDIUM |
| Installation of Drinking water Reverse Osmosis unit at Kodih 191 days beyond expected completion | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹8.00 L | 191 d | 0% | 42.8 | MEDIUM |
| Providing 2 chambered morturary Freezing Chamber equipment 290 days beyond expected completion | CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) | Recommended | ₹5.00 L | 290 d | 0% | 42.0 | MEDIUM |