643 works across 1 implementing agency, recommended by 12 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | 643 | 273 | ₹63.80 Cr | 128 | 27.2 | Rakesh N 9% of spend · 104 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Tejasvi Surya BANGALORE SOUTH | 132 | ₹12.32 Cr | 27 |
| G.C. Chandrashekhar Sitting Rajya Sabha | 115 | ₹7.06 Cr | 21 |
| Shobha Karandlaje BANGALORE NORTH | 114 | ₹11.92 Cr | 5 |
| Jaggesh Sitting Rajya Sabha | 113 | ₹14.19 Cr | 46 |
| Narayanasa K. Bhandage Sitting Rajya Sabha | 75 | ₹8.29 Cr | 13 |
| C N Manjunath BANGALORE RURAL | 32 | ₹1.46 Cr | 0 |
| K Sudhakar CHIKBALLAPUR | 27 | ₹1.33 Cr | 1 |
| P C Mohan BANGALORE CENTRAL | 19 | ₹2.59 Cr | 4 |
| Lahar Singh Siroya Sitting Rajya Sabha | 12 | ₹3.83 Cr | 7 |
| Nirmala Sitharaman Sitting Rajya Sabha | 2 | ₹25.00 L | 2 |
| Dharmasthala Veerendra Heggade Nominated Rajya Sabha | 1 | ₹5.00 L | 1 |
| Sudha Murty Nominated Rajya Sabha | 1 | ₹50.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 271 | ₹30.49 Cr | 57 |
| Water | 99 | ₹7.24 Cr | 20 |
| Education | 69 | ₹6.41 Cr | 29 |
| Street Lighting | 66 | ₹3.74 Cr | 8 |
| Community Buildings | 50 | ₹5.77 Cr | 3 |
| Drainage & Sanitation | 30 | ₹2.05 Cr | 4 |
| Equipment & Vehicles | 25 | ₹2.66 Cr | 2 |
| Health | 13 | ₹2.00 Cr | 1 |
| Religious & Cultural | 7 | ₹1.12 Cr | 2 |
| Sports | 6 | ₹1.82 Cr | 2 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Cement Concrete Road (C C Road) at Lakshmipu ₹3,000,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (501% above, 567 peer works) | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹30.00 L | 156 d | +501% | 68.8 | MEDIUM |
| Bangalore Urban District, Jayanagar Vidhanasabha constituenc ₹2,500,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (400% above, 567 peer works) | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹25.00 L | 132 d | +400% | 65.5 | MEDIUM |
| Bangalore Urban district, Jayanagar assembly constituency, w ₹2,500,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (400% above, 567 peer works) | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹25.00 L | 132 d | +400% | 65.5 | MEDIUM |
| Bangalore Urban district, Jayanagar assembly constituency, w ₹2,000,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (300% above, 567 peer works) | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹20.00 L | 132 d | +300% | 65.5 | MEDIUM |
| Construction of CC Road from the entrance of Kittaganahalli ₹12,000,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (2302% above, 567 peer works) | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹1.20 Cr | 98 d | +2302% | 60.7 | MEDIUM |
| New Bore Drilling Work Near Doddabasti Village Under Suliker ₹800,000 against a ₹499,518 median for Water works in BENGALURU URBAN (60% above, 225 peer works) | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹8.00 L | 162 d | +60% | 59.7 | MEDIUM |
| Concrete road development work. Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 691 d | +0% | 57.1 | MEDIUM |
| Concrete Road development work. Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 691 d | +0% | 57.1 | MEDIUM |
| C.C Drainage development work. Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 691 d | +0% | 57.1 | MEDIUM |
| Concrete Road development work. 693 days beyond expected completion | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 693 d | +0% | 57.1 | MEDIUM |
| Concrete Road development work from Tavarekere village to Ma 693 days beyond expected completion | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 693 d | +0% | 57.1 | MEDIUM |
| Road development work, Tavarekere Village, Tavarekere Grama 693 days beyond expected completion | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 693 d | +0% | 57.1 | MEDIUM |
| Concrete road development work, Lakkuppe Village, Channenaha 692 days beyond expected completion | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 692 d | +0% | 57.1 | MEDIUM |
| Concrete road development work, Lakkuppe Village, Channenaha 692 days beyond expected completion | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 692 d | +0% | 57.1 | MEDIUM |
| Concrete Road development work. 692 days beyond expected completion | BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) | Recommended | ₹5.00 L | 692 d | +0% | 57.1 | MEDIUM |