415 works across 1 implementing agency, recommended by 7 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) 5 high risk | 415 | 119 | ₹22.45 Cr | 285 | 40.5 | THIMMARAJU U H 2% of spend · 242 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Annasaheb Shankar Jolle CHIKKODI | 202 | ₹9.61 Cr | 124 |
| Mangal Suresh Angadi BELGAUM | 183 | ₹9.72 Cr | 146 |
| Anantkumar Hegde UTTARA KANNADA | 17 | ₹84.83 L | 9 |
| Jairam Ramesh Sitting Rajya Sabha | 9 | ₹1.87 Cr | 3 |
| Dharmasthala Veerendra Heggade Nominated Rajya Sabha | 2 | ₹30.00 L | 2 |
| Jaggesh Sitting Rajya Sabha | 1 | ₹5.00 L | 0 |
| Ramesh Chandappa Jigajinagi BIJAPUR | 1 | ₹4.95 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 352 | ₹17.59 Cr | 248 |
| Roads & Paving | 26 | ₹1.39 Cr | 17 |
| Education | 20 | ₹1.93 Cr | 13 |
| Other | 7 | ₹1.05 Cr | 1 |
| Religious & Cultural | 4 | ₹19.99 L | 2 |
| Water | 2 | ₹10.00 L | 2 |
| Drainage & Sanitation | 2 | ₹10.00 L | 1 |
| Sports | 1 | ₹5.00 L | 1 |
| Boundary & Protection | 1 | ₹4.98 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Hall ₹1,500,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (200% above, 447 peer works) | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹15.00 L | 609 d | +200% | 77.4 | HIGH |
| Construction of Sanskrutika Bhavan near Shri Basaveshwar ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works) | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹10.00 L | 561 d | +100% | 77.4 | HIGH |
| Construction of Sanskrutika Bhavan near Shri Veerbhadreshwar ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works) | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹10.00 L | 619 d | +100% | 77.4 | HIGH |
| Construction of Sanskrutika Bhavan near Shri Veerbhdreshwa ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works) | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹10.00 L | 561 d | +100% | 73.6 | HIGH |
| Road construction work ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BELAGAVI (200% above, 59 peer works) | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹15.00 L | 146 d | +200% | 72.7 | HIGH |
| Construction of Sanskrutika Bhavan near Shri Mahanta Duradun ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works) | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹10.00 L | 561 d | +100% | 66.7 | MEDIUM |
| Construction of Cultural Hall Near Shri Hanuman Temple Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹5.00 L | 691 d | 0% | 62.4 | MEDIUM |
| Construction of Cultural Hall Near Shri Laxmi Temple 698 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹5.00 L | 698 d | 0% | 62.3 | MEDIUM |
| Construction of Cultural Hall Near
Shri Mahadev Temple 698 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹5.00 L | 698 d | 0% | 62.3 | MEDIUM |
| Construction of HiTech Bus Shelter 698 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹4.50 L | 698 d | -10% | 62.1 | MEDIUM |
| Construction of HiTech Bus Shelter 698 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹4.50 L | 698 d | -10% | 62.1 | MEDIUM |
| Construction of HiTech Bus Shelter 698 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹4.50 L | 698 d | -10% | 62.1 | MEDIUM |
| Construction of Cultural Hall Near Shri Basaveshwar Temple 697 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹4.00 L | 697 d | -20% | 61.7 | MEDIUM |
| Construction of Cultural Hall Near Shri Hanuman Temple 697 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹4.00 L | 697 d | -20% | 61.7 | MEDIUM |
| Construction of Cultural Hall Near Shri Basaveshwar Temple 697 days beyond expected completion | BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) | Recommended | ₹3.00 L | 697 d | -40% | 61.1 | MEDIUM |