204 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | 204 | 83 | ₹5.62 Cr | 120 | 31.2 | MS CHANDRA BHUSHAN 67% of spend · 7 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Sunil Soren DUMKA | 195 | ₹5.33 Cr | 115 |
| Vijay Kumar Hansdak RAJMAHAL | 8 | ₹17.07 L | 5 |
| Pradip Kumar Varma Sitting Rajya Sabha | 1 | ₹12.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 167 | ₹4.42 Cr | 93 |
| Drainage & Sanitation | 11 | ₹30.00 L | 6 |
| Community Buildings | 10 | ₹28.50 L | 8 |
| Religious & Cultural | 8 | ₹30.50 L | 7 |
| Water | 5 | ₹13.50 L | 4 |
| Education | 2 | ₹6.00 L | 2 |
| Other | 1 | ₹12.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Building behind Thakurbadi Temple ₹500,000 against a ₹300,000 median for Religious & Cultural works in DUMKA (67% above, 11 peer works) | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹5.00 L | 588 d | +67% | 52.8 | MEDIUM |
| Construction of Paver Blocks in Bar Office ₹500,000 against a ₹300,000 median for Roads & Paving works in DUMKA (67% above, 319 peer works) | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹5.00 L | 588 d | +67% | 52.8 | MEDIUM |
| Construction of Stair Ghaat in Bada Bandh (Govt.) ₹500,000 against a ₹300,000 median for Religious & Cultural works in DUMKA (67% above, 11 peer works) | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹5.00 L | 591 d | +67% | 52.8 | MEDIUM |
| Construction of Drain with Cover from Late Umashankar's Home ₹400,000 against a ₹250,000 median for Drainage & Sanitation works in DUMKA (60% above, 16 peer works) | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹4.00 L | 664 d | +60% | 51.2 | MEDIUM |
| Construction of Drain and Bridge near Anmol Singh Home behin Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹4.00 L | 763 d | +33% | 47.8 | MEDIUM |
| Construction of PCC Road from Main Road to Kali Temple 600 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹2.50 L | 600 d | -17% | 45.3 | MEDIUM |
| Construction of PCC Road in Public Way from Birbal Singh Hom 664 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹2.50 L | 664 d | -17% | 44.1 | MEDIUM |
| Construction of PCC Road from Subhash Mandal's Home to Pradh 664 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹2.50 L | 664 d | -17% | 44.1 | MEDIUM |
| Repairing of Lohiya Building, Colouring & Paver Block Instal 664 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹2.50 L | 664 d | -17% | 44.1 | MEDIUM |
| Construction of Ghaat in Dhirnagar Govt. Pond in Village- Dh 664 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹2.50 L | 664 d | -17% | 44.1 | MEDIUM |
| Construction of PCC Road from Banyana Tree to River in Villa 664 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹2.50 L | 664 d | -17% | 44.1 | MEDIUM |
| Construction of PCC Road near Dubey Manda in Village- Bichko 664 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹3.00 L | 664 d | 0% | 44.0 | MEDIUM |
| Construction of PCC Road from Suklal Hembram's Home to REO R 664 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹3.00 L | 664 d | 0% | 44.0 | MEDIUM |
| Repairing Work of Hall of Saraswati Sisu Vidya Mandir School 547 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹3.00 L | 547 d | 0% | 44.0 | MEDIUM |
| Repair & Colorant of Community Building 591 days beyond expected completion | DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) | Recommended | ₹3.50 L | 591 d | +17% | 43.6 | MEDIUM |