87 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | 87 | 30 | ₹3.64 Cr | 3 | 15.4 | Alyas ahmad mir 27% of spend · 25 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Aga Syed Ruhullah Mehdi SRINAGAR | 86 | ₹3.14 Cr | 2 |
| Sajjad Ahmad Kichloo Sitting Rajya Sabha | 1 | ₹50.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Drainage & Sanitation | 22 | ₹60.71 L | 1 |
| Roads & Paving | 21 | ₹69.02 L | 1 |
| Boundary & Protection | 12 | ₹34.81 L | 0 |
| Water | 8 | ₹22.75 L | 0 |
| Sports | 8 | ₹44.26 L | 0 |
| Street Lighting | 7 | ₹38.67 L | 0 |
| Religious & Cultural | 5 | ₹33.00 L | 0 |
| Health | 3 | ₹57.74 L | 1 |
| Community Buildings | 1 | ₹2.92 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| raising of mainholes at various locations within the chanpor ₹800,000 against a ₹210,894 median for Drainage & Sanitation works in SRINAGAR (279% above, 22 peer works) | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹8.00 L | 136 d | +279% | 47.8 | MEDIUM |
| construction of road with concrete culvert from bali mohalla ₹2,500,000 against a ₹198,000 median for Roads & Paving works in SRINAGAR (1163% above, 21 peer works) | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹25.00 L | 135 d | +1163% | 47.6 | MEDIUM |
| Construction of Auditorium at Sher-i-Kashmir Institute of Me Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹50.00 L | — | 0% | 41.5 | MEDIUM |
| Laying of pipelines from the fire service station to mohd su 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹2.00 L | 173 d | +34% | 36.4 | LOW |
| Development of pipelines and drain near the house of rayees 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹1.16 L | 173 d | -22% | 35.5 | LOW |
| Upgradation, construction of graveyard near hospital rainawa 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹4.24 L | 173 d | 0% | 34.5 | LOW |
| Renovation of public park at wantapora kawdara srinagar 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹3.50 L | 173 d | -13% | 34.4 | LOW |
| Electrical equipement installation at PHC lal bazar srinagar 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹3.50 L | 173 d | 0% | 34.4 | LOW |
| Construction of channeling and fencing around the graveyard 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹3.00 L | 173 d | +9% | 34.1 | LOW |
| Construction of retaining wall on the existing wall near the 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹2.14 L | 173 d | -22% | 34.0 | LOW |
| Construction of wooden culvert near AV traders and others ne 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹2.06 L | 173 d | +4% | 34.0 | LOW |
| Construction of drain from the house of farooq ahmad lone to 173 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹2.50 L | 173 d | +19% | 33.9 | LOW |
| laying of two water pipes from the house of iqbal parray, ab 148 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹1.00 L | 148 d | -33% | 31.5 | LOW |
| upgradation of madr i mahrban stadium at palpora srinagar 155 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹4.00 L | 155 d | 0% | 31.4 | LOW |
| providing mechanical roller for tulkaul sports stadium 155 days beyond expected completion | SRINAGAR(DEPUTY COMMISSIONER SRINAGAR_IDA) | Recommended | ₹4.00 L | 155 d | 0% | 31.4 | LOW |