234 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) 4 high risk | 234 | 118 | ₹18.77 Cr | 10 | 22.1 | CONNECTWAVE INTEGRATIONS PVT LTD 48% of spend · 54 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| S. Jaishankar Sitting Rajya Sabha | 163 | ₹17.11 Cr | 10 |
| Mansukhbhai Dhanjibhai Vasava BHARUCH | 40 | ₹85.77 L | 0 |
| Gitaben Vajesingbhai Rathva CHHOTA UDAIPUR | 30 | ₹75.38 L | 0 |
| Parmar Jashvantsinh Salamsinh Sitting Rajya Sabha | 1 | ₹5.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 151 | ₹7.44 Cr | 3 |
| Roads & Paving | 42 | ₹1.53 Cr | 1 |
| Water | 22 | ₹34.38 L | 0 |
| Drainage & Sanitation | 5 | ₹12.58 L | 0 |
| Religious & Cultural | 4 | ₹1.57 Cr | 1 |
| Health | 4 | ₹7.08 Cr | 4 |
| Boundary & Protection | 3 | ₹12.00 L | 0 |
| Equipment & Vehicles | 2 | ₹5.98 L | 0 |
| Community Buildings | 1 | ₹50.00 L | 1 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of New LDR Complex Building (Maternity Complex Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹1.77 Cr | 356 d | 0% | 72.7 | HIGH |
| Construction of New LDR Complex Building (Maternity Complex Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹1.77 Cr | 356 d | 0% | 72.7 | HIGH |
| Construction of New LDR Complex Building (Maternity Complex Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹1.77 Cr | 356 d | 0% | 72.7 | HIGH |
| Construction of New LDR Complex Building (Maternity Complex Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹1.77 Cr | 356 d | 0% | 72.7 | HIGH |
| To establish IPHS mandated Ayushman Arogya Mandir with Solar ₹15,080,100 against a ₹200,000 median for Religious & Cultural works in NARMADA (7440% above, 8 peer works) | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹1.51 Cr | 129 d | +7440% | 67.3 | MEDIUM |
| Construction of Gymnastic Landing Pit in Gymnastic Hall at C Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹50.00 L | 129 d | 0% | 60.8 | MEDIUM |
| Setting Up Solar Roof Top System at Government Primary Schoo 356 days beyond expected completion | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹3.00 L | 356 d | -40% | 57.6 | MEDIUM |
| Setting Up Solar Roof Top System at Government Primary Schoo 356 days beyond expected completion | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹3.00 L | 356 d | -40% | 57.6 | MEDIUM |
| Construction of Road (650 meter) from Kumbhiya Main Road to ₹4,562,815 against a ₹250,000 median for Roads & Paving works in NARMADA (1725% above, 83 peer works) | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Completed | ₹45.63 L | — | +1725% | 49.3 | MEDIUM |
| Purchase of Transport Vehicle at Jawahar Navodaya Vidyalaya, ₹923,357 against a ₹500,000 median for Education works in NARMADA (85% above, 302 peer works) | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Completed | ₹9.23 L | — | +85% | 45.5 | MEDIUM |
| mohanbhai vaistabhai naa faliya maa mini jaal dhara nu kaam 663 days beyond expected completion | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹2.00 L | 663 d | +33% | 38.4 | LOW |
| Work of new benches (RCC benches) at Bhadiji Mandir in Bhada 638 days beyond expected completion | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹1.00 L | 638 d | -50% | 38.0 | LOW |
| Construction of new benches (RCC benches) at Nilakath Dham p 638 days beyond expected completion | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Recommended | ₹1.00 L | 638 d | 0% | 38.0 | LOW |
| Construction of New Girl's Toilet at Khaidipada Primary Scho 100% similarity with another nearby work | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Completed | ₹2.80 L | — | +20% | 29.4 | LOW |
| Construction of New Girl's Toilet at Gansinda Primary School 100% similarity with another nearby work | NARMADA(DISTRICT COLLECTOR NARMADA_IDA) | Completed | ₹2.80 L | — | +20% | 29.4 | LOW |