6 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) | 6 | 0 | ₹66.50 L | 5 | 50.1 | Mahadev Construction co 13% of spend · 21 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Narain Dass Gupta Sitting Rajya Sabha | 6 | ₹66.50 L | 5 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Sports | 5 | ₹50.25 L | 5 |
| Street Lighting | 1 | ₹16.25 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of 400 Mtr Track in Stadium ₹1,467,000 against a ₹537,000 median for Sports works in SONIPAT (173% above, 19 peer works) | SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) | Recommended | ₹14.67 L | 113 d | +173% | 65.3 | MEDIUM |
| Construction of Basket Ball Court in Stadium ₹964,000 against a ₹537,000 median for Sports works in SONIPAT (80% above, 19 peer works) | SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) | Recommended | ₹9.64 L | 113 d | +80% | 60.2 | MEDIUM |
| Provision of work relate to Walking Track in Stadium ₹2,000,000 against a ₹537,000 median for Sports works in SONIPAT (272% above, 19 peer works) | SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) | Recommended | ₹20.00 L | — | +272% | 49.6 | MEDIUM |
| Construction of Volley Ball Court in Stadium 113 days beyond expected completion | SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) | Recommended | ₹57,000 | 113 d | -89% | 48.1 | MEDIUM |
| Installation of Open Gym in Stadium 113 days beyond expected completion | SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) | Recommended | ₹5.37 L | 113 d | 0% | 46.2 | MEDIUM |
| Provision of work relate to lighting and poles Installation 100% similarity with another nearby work | SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) | Recommended | ₹16.25 L | — | 0% | 31.4 | LOW |