51 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | 51 | 16 | ₹6.73 Cr | 10 | 26.5 | Samriddhi Enterprises 58% of spend · 21 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Bhojraj Nag KANKER | 50 | ₹3.73 Cr | 9 |
| Rajeev Shukla Sitting Rajya Sabha | 1 | ₹3.00 Cr | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 28 | ₹4.58 Cr | 3 |
| Community Buildings | 11 | ₹90.63 L | 4 |
| Religious & Cultural | 6 | ₹55.00 L | 2 |
| Roads & Paving | 3 | ₹20.00 L | 1 |
| Sports | 2 | ₹39.98 L | 0 |
| Drainage & Sanitation | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Antagarh Block ke Govt Middel High School Higher Secondery S ₹950,000 against a ₹500,000 median for Education works in UTTAR BASTAR KANKER (90% above, 31 peer works) | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹9.50 L | 182 d | +90% | 61.9 | MEDIUM |
| additional rooms Sarashwatii Shishu Mandir Koyalibeda ke pa 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹10.00 L | 195 d | 0% | 55.0 | MEDIUM |
| additional rooms Sarashwatii Shishu Mandir Kewati ke pass 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹10.00 L | 195 d | 0% | 55.0 | MEDIUM |
| community halls ₹1,000,000 against a ₹499,164 median for Community Buildings works in UTTAR BASTAR KANKER (100% above, 58 peer works) | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹10.00 L | — | +100% | 52.8 | MEDIUM |
| I propose the construction of a state-ofthe-art public (digi ₹30,000,000 against a ₹500,000 median for Education works in UTTAR BASTAR KANKER (5900% above, 31 peer works) | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Completed | ₹3.00 Cr | — | +5900% | 52.8 | MEDIUM |
| Construction of community centers and community halls ₹700,000 against a ₹499,164 median for Community Buildings works in UTTAR BASTAR KANKER (40% above, 58 peer works) | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹7.00 L | 195 d | +40% | 42.9 | MEDIUM |
| community centers Andhewada Badepara ₹700,000 against a ₹499,164 median for Community Buildings works in UTTAR BASTAR KANKER (40% above, 58 peer works) | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹7.00 L | 195 d | +40% | 42.9 | MEDIUM |
| community centers Koyalibeda PV 110 ₹700,000 against a ₹499,164 median for Community Buildings works in UTTAR BASTAR KANKER (40% above, 58 peer works) | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹7.00 L | 195 d | +40% | 42.9 | MEDIUM |
| Puliya Nirman Naveen Bala de Jameen Ke Pass PV 33 Udaipur 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹10.00 L | 195 d | 0% | 42.3 | MEDIUM |
| Durgukondal Block ke Govt Middel High School Higher Seconder Completed work has no photographic documentation on record | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Completed | ₹9.50 L | — | +90% | 41.5 | MEDIUM |
| School ke pass P Jawhar Lal Nehru Ward Charama 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹5.00 L | 195 d | 0% | 39.8 | LOW |
| additional Rooms 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹5.00 L | 195 d | 0% | 39.8 | LOW |
| Additional rooms Devinawagaon Bazar Chounk ke Pass 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹5.00 L | 195 d | 0% | 39.8 | LOW |
| additional rooms Narayanpur Yadav Samaj Bhumi ke pass 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹5.00 L | 195 d | +0% | 39.8 | LOW |
| additional rooms Chotekapsi Kali mandir ke pass 195 days beyond expected completion | Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) | Recommended | ₹5.00 L | 195 d | 0% | 39.8 | LOW |