Open this link on a larger screen to see the verification queue.
83 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | 83 | 73 | ₹6.36 Cr | 3 | 17.4 | Rameshwar Gupta 22% of spend · 46 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Gomati Sai RAIGARH | 49 | ₹3.29 Cr | 2 |
| Ranjeet Ranjan Sitting Rajya Sabha | 31 | ₹2.47 Cr | 0 |
| Phulo Devi Netam Sitting Rajya Sabha | 3 | ₹60.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 26 | ₹2.83 Cr | 1 |
| Street Lighting | 21 | ₹1.04 Cr | 0 |
| Religious & Cultural | 16 | ₹75.49 L | 1 |
| Community Buildings | 11 | ₹59.19 L | 1 |
| Drainage & Sanitation | 4 | ₹61.00 L | 0 |
| Sports | 3 | ₹44.00 L | 0 |
| Water | 2 | ₹8.35 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Community Hall Extension Lakhjhar ₹1,000,000 against a ₹549,892 median for Community Buildings works in JASHPUR (82% above, 12 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹10.00 L | 644 d | +82% | 46.4 | MEDIUM |
| Gram maini me RCC puliya nirman karya sarna road ke pas ₹2,000,000 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (100% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹20.00 L | — | +100% | 46.0 | MEDIUM |
| Sanskrit Manch Nirman Kharibahar ₹500,000 against a ₹300,000 median for Religious & Cultural works in JASHPUR (67% above, 17 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹5.00 L | 715 d | +67% | 42.6 | MEDIUM |
| Cultural Stage Creation Lakraghara 715 days beyond expected completion | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹2.50 L | 715 d | -17% | 35.5 | LOW |
| Pavilion Construction Deepa Gamhariya 644 days beyond expected completion | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹4.00 L | 644 d | 0% | 34.4 | LOW |
| Construction of a culvert on the main road to the Aarakona a ₹1,499,843 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (50% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹15.00 L | — | +50% | 33.5 | LOW |
| Construction of a culvert on the main road to the Sardih Dam ₹1,499,843 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (50% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹15.00 L | — | +50% | 33.5 | LOW |
| Construction of a culvert on the main road to Sarna School a ₹1,499,843 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (50% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Recommended | ₹15.00 L | — | +50% | 33.5 | LOW |
| Construction of road from Main Road to Sarana Approach Road, ₹1,499,677 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (50% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Completed | ₹15.00 L | — | +50% | 33.5 | LOW |
| Construction of road from Main Road to Ten Ghat, Village Pan ₹1,499,836 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (50% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Completed | ₹15.00 L | — | +50% | 33.5 | LOW |
| Construction / development of road
from Suikona to Kudagada ₹1,499,544 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (50% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Completed | ₹15.00 L | — | +50% | 33.4 | LOW |
| RCC Pulia Culvert Construction at Sarna Crusher Road Janpad ₹1,498,218 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (50% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Completed | ₹14.98 L | — | +50% | 33.4 | LOW |
| Road work from the main road to Machari Dumarpani Basti in G ₹1,449,626 against a ₹1,000,000 median for Roads & Paving works in JASHPUR (45% above, 62 peer works) | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Completed | ₹14.50 L | — | +45% | 32.2 | LOW |
| Construction of RCC culvert on Sarna approach road, Village 100% similarity with another nearby work | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Completed | ₹13.00 L | — | +30% | 30.6 | LOW |
| Compound Building Krishna Temple Complex Illa Completed work has no photographic documentation on record | JASHPUR(DISTRICT COLLECTOR JASHPUR_IDA) | Completed | ₹6.00 L | — | +100% | 30.5 | LOW |