79 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | 79 | 45 | ₹6.48 Cr | 16 | 24.6 | GRAM PANCHAYAT DERADIH 22% of spend · 40 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Brijmohan Agrawal RAIPUR | 38 | ₹2.98 Cr | 0 |
| Ranjeet Ranjan Sitting Rajya Sabha | 34 | ₹2.94 Cr | 16 |
| Kamlesh Jangde JANJGIR CHAMPA | 7 | ₹56.98 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 29 | ₹2.25 Cr | 11 |
| Community Buildings | 25 | ₹2.14 Cr | 3 |
| Education | 9 | ₹84.95 L | 1 |
| Water | 4 | ₹15.74 L | 0 |
| Religious & Cultural | 3 | ₹20.99 L | 0 |
| Drainage & Sanitation | 3 | ₹22.00 L | 0 |
| Sports | 3 | ₹29.99 L | 1 |
| Street Lighting | 2 | ₹19.98 L | 0 |
| Boundary & Protection | 1 | ₹15.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of common work sheds and common covered sitting ₹1,000,000 against a ₹674,500 median for Community Buildings works in BALODABAZAR-BHATAPARA (48% above, 40 peer works) | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Recommended | ₹10.00 L | 244 d | +48% | 57.9 | MEDIUM |
| Construction of community center for Sahu Samaj in Deradih v Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹19.99 L | — | +196% | 50.4 | MEDIUM |
| Construction of a CC Road from Guri Chowk to Transformer in Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹15.00 L | — | +200% | 50.4 | MEDIUM |
| Construction of community centers and community halls at Sah Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹20.00 L | — | +197% | 50.4 | MEDIUM |
| Construction of CC Road from the Ram Say Shop to Kirtan Ghar Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹10.00 L | — | +100% | 50.4 | MEDIUM |
| Construction of CC Road from the residence of Pustam to Fule Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹10.00 L | — | +100% | 50.4 | MEDIUM |
| Construction of CC Road from the residence of Komal Sahu to Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹10.00 L | — | +100% | 50.4 | MEDIUM |
| Construction of CC Road from the residence of Mangal Das to Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹10.00 L | — | +100% | 50.4 | MEDIUM |
| Construction of CC road from the house of Tulshi God to the Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹10.00 L | — | +100% | 50.4 | MEDIUM |
| Construction of a CC Road from the School to Firatram Sahu's Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹10.00 L | — | +100% | 50.4 | MEDIUM |
| Construction of a C.C. Road from the house of Pramod Devanga Completed work has no photographic documentation on record | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Completed | ₹10.00 L | — | +100% | 50.4 | MEDIUM |
| Construction of CC road from the house of Mahendra Kashayp t ₹1,000,000 against a ₹500,000 median for Roads & Paving works in BALODABAZAR-BHATAPARA (100% above, 68 peer works) | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Recommended | ₹10.00 L | 32 d | +100% | 50.3 | MEDIUM |
| Leveling of the playground in Village Panchayat Nawrangpur K 145 days beyond expected completion | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Recommended | ₹10.00 L | 145 d | 0% | 49.6 | MEDIUM |
| Construction of a Cement Concrete (CC) Road from the Electri ₹1,000,000 against a ₹500,000 median for Roads & Paving works in BALODABAZAR-BHATAPARA (100% above, 68 peer works) | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Recommended | ₹10.00 L | — | +100% | 45.9 | MEDIUM |
| CC Road construction from Rohits house to Mohans house in Ko ₹1,000,000 against a ₹500,000 median for Roads & Paving works in BALODABAZAR-BHATAPARA (100% above, 68 peer works) | Balodabazar-Bhatapara(Collector Baloda Bazar_IDA) | Recommended | ₹10.00 L | — | +100% | 45.9 | MEDIUM |