11 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | 11 | 1 | ₹72.00 L | 7 | 33.9 | SHAZIBUL HASSAN MOLLAH 51% of spend · 3 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Rakibul Hussain DHUBRI | 11 | ₹72.00 L | 7 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 4 | ₹16.50 L | 4 |
| Education | 2 | ₹20.00 L | 1 |
| Religious & Cultural | 2 | ₹7.50 L | 2 |
| Equipment & Vehicles | 1 | ₹9.00 L | 0 |
| Health | 1 | ₹9.00 L | 0 |
| Other | 1 | ₹10.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Additional Classroom of Hatsingimari College 183 days beyond expected completion | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹10.00 L | 183 d | 0% | 46.4 | MEDIUM |
| Construction of Waiting Shed at Hatsingimari 352 days beyond expected completion | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹5.00 L | 352 d | 0% | 45.9 | MEDIUM |
| Construction of Waiting Shed at Jordanga Kuchnimara 352 days beyond expected completion | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹5.00 L | 352 d | 0% | 45.9 | MEDIUM |
| Repair of Community Hall at Tumni Kolabari Bazar 183 days beyond expected completion | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹2.50 L | 183 d | 0% | 43.4 | MEDIUM |
| Construction of Community Hall near Sahapara Mankachar 174 days beyond expected completion | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹4.00 L | 174 d | 0% | 43.0 | MEDIUM |
| Construction of Janajah Ghar at Jhalerchar Kabristhan 174 days beyond expected completion | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹5.00 L | 174 d | 0% | 42.7 | MEDIUM |
| Construction of Markaz at Tumni 174 days beyond expected completion | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹2.50 L | 174 d | 0% | 42.4 | MEDIUM |
| Porviding One Abbulance Facilities for Hatsingimari Civil Ho Implementing agency has a 82% delay rate across its projects | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Completed | ₹9.00 L | — | 0% | 18.7 | LOW |
| Porviding 1 (One) Abbulance Facilities for South Salmara BPH Implementing agency has a 82% delay rate across its projects | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹9.00 L | — | 0% | 14.9 | LOW |
| Pro Siltation Measures at DS of Sukchar Bazar under MPLAD f Implementing agency has a 82% delay rate across its projects | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹10.00 L | — | 0% | 14.8 | LOW |
| Const. of Digital Classroom at South Salmara College, South Implementing agency has a 82% delay rate across its projects | SOUTH SALMARA MANCACHAR(Deputy Commissioner South Salmara Mankachar_IDA) | Recommended | ₹10.00 L | — | 0% | 14.8 | LOW |