103 works across 1 implementing agency, recommended by 7 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | 103 | 10 | ₹10.97 Cr | 8 | 14.5 | EHIKA Groups 11% of spend · 33 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Chandra Sekhar Pemmasani GUNTUR | 96 | ₹9.51 Cr | 5 |
| Yerram Venkata Subba Reddy Sitting Rajya Sabha | 2 | ₹10.00 L | 0 |
| S Niranjan Reddy Sitting Rajya Sabha | 1 | ₹50.00 L | 1 |
| Lavu Sri Krishna Devarayalu NARASARAOPET | 1 | ₹4.17 L | 0 |
| Balashowry Vallabhaneni MACHILIPATNAM | 1 | ₹2.00 L | 0 |
| V. Vijayendra Prasad Nominated Rajya Sabha | 1 | ₹50.00 L | 1 |
| Ryaga Krishnaiah Sitting Rajya Sabha | 1 | ₹30.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 61 | ₹4.62 Cr | 3 |
| Community Buildings | 18 | ₹3.02 Cr | 2 |
| Education | 6 | ₹1.61 Cr | 1 |
| Boundary & Protection | 6 | ₹77.00 L | 2 |
| Religious & Cultural | 5 | ₹54.05 L | 0 |
| Drainage & Sanitation | 3 | ₹19.96 L | 0 |
| Water | 2 | ₹10.00 L | 0 |
| Health | 1 | ₹4.17 L | 0 |
| Equipment & Vehicles | 1 | ₹6.61 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of BC Community Hall in Garikapadu Village, Kak ₹3,000,000 against a ₹1,500,000 median for Community Buildings works in GUNTUR (100% above, 27 peer works) | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹30.00 L | 105 d | +100% | 61.5 | MEDIUM |
| Construction of slab culvert at Turakapalem H of Dokiparru o ₹2,000,000 against a ₹500,000 median for Roads & Paving works in GUNTUR (300% above, 178 peer works) | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹20.00 L | 217 d | +300% | 51.9 | MEDIUM |
| Construction of burial ground compound wall in Prathipadu (G ₹1,500,000 against a ₹700,000 median for Boundary & Protection works in GUNTUR (114% above, 13 peer works) | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹15.00 L | 217 d | +114% | 51.9 | MEDIUM |
| Providing Amenities to Community Hall in Narakoduru village ₹5,000,000 against a ₹1,500,000 median for Community Buildings works in GUNTUR (233% above, 27 peer works) | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹50.00 L | 235 d | +233% | 51.9 | MEDIUM |
| Providing RCC drain from Nulkapeta old Sachivalayam back sid ₹2,600,000 against a ₹500,000 median for Roads & Paving works in GUNTUR (420% above, 178 peer works) | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹26.00 L | 255 d | +420% | 51.9 | MEDIUM |
| Development improvement of facilities in the library in the Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹50.00 L | 71 d | 0% | 50.4 | MEDIUM |
| Construction of Compound Wall and Main Gate Fixing at Kummar ₹1,500,000 against a ₹700,000 median for Boundary & Protection works in GUNTUR (114% above, 13 peer works) | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹15.00 L | 160 d | +114% | 49.1 | MEDIUM |
| Solar Energy System installation at Sri Patibandla Sitaramai ₹5,000,000 against a ₹500,000 median for Roads & Paving works in GUNTUR (900% above, 178 peer works) | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Completed | ₹50.00 L | — | +900% | 46.9 | MEDIUM |
| Providing ceremony rooms location at burial ground in Angala Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹25.00 L | 165 d | 0% | 39.6 | LOW |
| Providing Classrooms for SRR Municipal Corporation High Scho Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹25.00 L | 165 d | 0% | 39.6 | LOW |
| Construction of Karma shala building in Hindu Burial ground 217 days beyond expected completion | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹10.00 L | 217 d | 0% | 36.9 | LOW |
| Fixing of New Connection & additional load in ESI Hospital N 349 days beyond expected completion | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹4.17 L | 349 d | 0% | 35.8 | LOW |
| Construction of retaining wall near Foot over bridge in Mora 255 days beyond expected completion | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹2.00 L | 255 d | -60% | 34.9 | LOW |
| Providing internal CC roads in Pamulapadu (V) of Tadikonda M 217 days beyond expected completion | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 34.1 | LOW |
| Providing internal CC roads in Vemavaram (V) of Phirangipura 217 days beyond expected completion | GUNTUR(DISTRICT COLLECTOR GUNTUR_IDA) | Recommended | ₹5.00 L | 217 d | 0% | 34.1 | LOW |