| 1 | From Banki tindola - road sampark marg to Bhavi Bharat inter Roads & Paving — Bara Banki(DISTRICT MAGISTRATE BARABANKI_IDA) - ₹2,500,000 against a ₹1,167,000 median for Roads & Paving works in BARA BANKI (114% above, 35 peer works)
- 262 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 2 payments still in progress, oldest 950 days
| BARA BANKI | ₹25.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Construction of two class rooms in Bhagwat Jha Azad Degree C Education — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹1,000,000 against a ₹249,745 median for Education works in JAMTARA (300% above, 46 peer works)
- 430 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 3 | Banipur Road se Ramswaroop ke khet ke pas Khanba ki aor DevS Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 84% of this agency's ₹50,485,526 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 29 vendors and 192 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 4 | Jagdish ke khet se Yogendra ki baithak ki aur Dev singh ka p Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 84% of this agency's ₹50,485,526 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 29 vendors and 192 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 5 | PASSENGERS IN RURAL AREAS WHO DEPEND ON PUBLIC TRANSPORT CAN Community Buildings — Bengaluru South(DEPUTY COMMISSIONER RAMANAGARA_IDA) - ₹1,200,000 against a ₹500,000 median for Community Buildings works in BENGALURU SOUTH (140% above, 133 peer works)
- 586 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 94% of this agency's ₹55,848,699 spend went to one vendor (KATANTAKA STATE HABITAT CENTRE), across 8 vendors and 97 transactions
| BENGALURU SOUTH | ₹12.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 6 | Construction of rooms in school and colleges Education — KAUSHAMBI(DISTRICT MAGISTRAE KAUSHAMBI_IDA) - ₹500,000 against a ₹21,497 median for Education works in KAUSHAMBI (2226% above, 950 peer works)
- 652 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 79% of this agency's ₹40,954,012 spend went to one vendor (Sunny Enterprises), across 15 vendors and 162 transactions
| KAUSHAMBI | ₹5.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 7 | Construction of rooms in school and colleges Education — KAUSHAMBI(DISTRICT MAGISTRAE KAUSHAMBI_IDA) - ₹500,000 against a ₹21,497 median for Education works in KAUSHAMBI (2226% above, 950 peer works)
- 652 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 79% of this agency's ₹40,954,012 spend went to one vendor (Sunny Enterprises), across 15 vendors and 162 transactions
| KAUSHAMBI | ₹5.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 8 | community hall nirman Community Buildings — RAJGARH(DISTRICT COLLECTOR RAJGARH_IDA) - ₹1,000,000 against a ₹306,328 median for Community Buildings works in RAJGARH (226% above, 53 peer works)
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 78% of this agency's ₹80,688,034 spend went to one vendor (MP Agro Biaora), across 19 vendors and 490 transactions
| RAJGARH | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 9 | Construction Teenshed at Trimurti dham, Gram Panchayat Umri, Religious & Cultural — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹995,000 against a ₹250,000 median for Religious & Cultural works in BHIND (298% above, 10 peer works)
- 191 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹9.95 L | HIGH 85
cost 25delay 25duplication 20 | |
| 10 | Asphalting of Naidu Street at ward No 10 of Chikkamagaluru C Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹3,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (500% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹30.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 11 | Asphalting of Shankarapura Road Chikkamagaluru CMC limit Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (300% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹20.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 12 | Development of Road from Hosapura Harijan colony to Chennag Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹5,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (900% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹50.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 13 | Development of Road from Kushalanagara Village to K.M. Road Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹2,500,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (400% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹25.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 14 | Development of Road from Danakkihara Village to Koodlu Villa Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (200% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹15.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 15 | Development Menasinahadya to Guddemane tribal colony Roa Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (140% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹12.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 16 | Development of Road from Mavinamarada kattehole to Santheke Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (300% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹20.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 17 | Development of Footpath Opposite side CUDA Water Tank of K Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (100% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 18 | Construction of concrete Road at Ballavara Village of Nan Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (100% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 19 | Continued road development of Ranganathaswamy Temple of Udev Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (100% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 20 | Construction of road at Paramanaghatta Anjaneya Temple at G Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (100% above, 257 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 21 | Construction of Girls Toilet at Primary school of Machagonda Drainage & Sanitation — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹2,800,000 against a ₹500,000 median for Drainage & Sanitation works in CHIKKAMAGALURU (460% above, 22 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹28.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 22 | To build toilet at Govt First Grade College of Menasur at N Drainage & Sanitation — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,500,000 against a ₹500,000 median for Drainage & Sanitation works in CHIKKAMAGALURU (200% above, 22 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹15.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 23 | To build A Hall at Davana Primary School of Kanoor villag Education — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Education works in CHIKKAMAGALURU (100% above, 34 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 24 | Development of Drain at Krishnapura Village (Gunjalakatte) U Drainage & Sanitation — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in CHIKKAMAGALURU (100% above, 22 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 25 | Construction of CC drain Yerebailu ovillage Malalichinnenaha Drainage & Sanitation — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in CHIKKAMAGALURU (100% above, 22 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |