| 1 | Construction of community hall in sahilong in dumargadi pan Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹500,000 median for Community Buildings works in KHUNTI (140% above, 30 peer works)
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Construction of community hall in sahilong in dumargadi pan Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹500,000 median for Community Buildings works in KHUNTI (140% above, 30 peer works)
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹12.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 3 | Construction of boundary wall near aamreshwar dham under tor Boundary & Protection — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹10.00 L | HIGH 76
delay 25duplication 20cost 16 | |
| 4 | Boring in Sarashwati shishu mandir murhu, salehatu under Mur Religious & Cultural — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹3.50 L | HIGH 72
delay 25duplication 20agency 15 | |
| 5 | Construction of boundary wall near aamreshwar dham under tor Boundary & Protection — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹10.00 L | HIGH 71
delay 25duplication 20cost 16 | |
| 6 | Construction of platform (Chabutra) in kota village, sargeya Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 730 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹2.00 L | HIGH 70
delay 25duplication 20agency 15 | |
| 7 | Boring in Sarashwati shishu mandir murhu, salehatu under Mur Religious & Cultural — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹3.50 L | MEDIUM 68
delay 25duplication 20cost 13 | |
| 8 | Construction of platform (Chabutra) in kota village, sargeya Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 730 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹2.00 L | MEDIUM 66
delay 25duplication 20cost 11 | |
| 9 | Construction of guard wall on the road going from Khunti Mah Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,300,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (225% above, 113 peer works)
- 364 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹13.00 L | MEDIUM 65 | |
| 10 | Construction of PCC road in Singha Dulua of Kunjla Panchayat Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (200% above, 113 peer works)
- 364 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | MEDIUM 65 | |
| 11 | Construction of community building in Mahadev Manda under Kh Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,100,000 against a ₹500,000 median for Community Buildings works in KHUNTI (120% above, 30 peer works)
- 364 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹11.00 L | MEDIUM 65 | |
| 12 | Construction of two rooms in the school in Barbanda Village Education — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,000,000 against a ₹450,000 median for Education works in KHUNTI (122% above, 8 peer works)
- 382 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹10.00 L | MEDIUM 65 | |
| 13 | Construction of PCC road in Sarengadih Tangra Toli. Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (150% above, 113 peer works)
- 382 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹10.00 L | MEDIUM 65 | |
| 14 | Construction of PCC and paver block path from Khunti Mahil P Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (200% above, 113 peer works)
- 383 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | MEDIUM 65 | |
| 15 | Construction of paver block path from Bukan Pahan's house to Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,000,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (150% above, 113 peer works)
- 383 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹10.00 L | MEDIUM 65 | |
| 16 | Construction of two rooms in Lutheran Middle School at Umbul Education — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹450,000 median for Education works in KHUNTI (167% above, 8 peer works)
- 383 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | MEDIUM 65 | |
| 17 | Construction of Multipurpose building in Navkel Mandatanr, V Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,068,000 against a ₹500,000 median for Community Buildings works in KHUNTI (114% above, 30 peer works)
- 574 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹10.68 L | MEDIUM 60 | |
| 18 | Construction of residential tranning building hall in villag Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,450,000 against a ₹500,000 median for Community Buildings works in KHUNTI (190% above, 30 peer works)
- 749 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹14.50 L | MEDIUM 60 | |
| 19 | Construction of a Community Building at village Galalong of Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,450,000 against a ₹500,000 median for Community Buildings works in KHUNTI (190% above, 30 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹14.50 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 20 | Construction of PCC road in Mahil (Jamtoli) under Murhu Bloc Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹650,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (62% above, 113 peer works)
- 264 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹6.50 L | MEDIUM 55 | |
| 21 | Construction of a Community Building at village Galalong of Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,450,000 against a ₹500,000 median for Community Buildings works in KHUNTI (190% above, 30 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹14.50 L | MEDIUM 55
cost 25duplication 20agency 10 | |
| 22 | Renovation of old hall in Khunti Club. Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹800,000 against a ₹500,000 median for Community Buildings works in KHUNTI (60% above, 30 peer works)
- 382 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹8.00 L | MEDIUM 55 | |
| 23 | Construction of PCC road on the path leading to cremation gr Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (200% above, 113 peer works)
- 107 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | MEDIUM 55 | |
| 24 | Construction of PCC road from Khunti Mahil main road to Baga Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (200% above, 113 peer works)
- 107 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | MEDIUM 55 | |
| 25 | Construction of PCC road from near Rural Works Department Of Roads & Paving — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹600,000 against a ₹400,000 median for Roads & Paving works in KHUNTI (50% above, 113 peer works)
- 364 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹6.00 L | MEDIUM 52 | |