| 1 | Construction of Community Hall Community Buildings — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹4,000,000 against a ₹1,000,000 median for Community Buildings works in MORENA (300% above, 45 peer works)
- 703 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹40.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 2 | Purchase of 03 mobile water tankers ( 5500 Lts Tyre Size 900 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹485,439 against a ₹161,813 median for Water works in MORENA (200% above, 45 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹4.85 L | HIGH 81
cost 25delay 25duplication 20 | |
| 3 | Purchase of 02 mobile water tankers ( 5500 Lts Tyre Size 900 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹323,626 against a ₹161,813 median for Water works in MORENA (100% above, 45 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹3.24 L | HIGH 81
cost 25delay 25duplication 20 | |
| 4 | Purchase of 03 mobile water tankers ( 5500 Lts Tyre Size 900 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹485,439 against a ₹161,813 median for Water works in MORENA (200% above, 45 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹4.85 L | HIGH 81
cost 25delay 25duplication 20 | |
| 5 | Purchase of 02 mobile water tankers ( 5500 Lts Tyre Size 900 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹323,626 against a ₹161,813 median for Water works in MORENA (100% above, 45 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹3.24 L | HIGH 81
cost 25delay 25duplication 20 | |
| 6 | Purchase of 02 mobile water tankers ( 5500 Lts Tyre Size 900 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹323,626 against a ₹161,813 median for Water works in MORENA (100% above, 45 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹3.24 L | HIGH 81
cost 25delay 25duplication 20 | |
| 7 | Purchase of 02 mobile water tankers ( 5500 Lts Tyre Size 900 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹326,352 against a ₹161,813 median for Water works in MORENA (102% above, 45 peer works)
- 713 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹3.26 L | HIGH 81
cost 25delay 25duplication 20 | |
| 8 | construction of COmmunity Hall Community Buildings — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in MORENA (50% above, 45 peer works)
- 703 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹15.00 L | HIGH 72
delay 25duplication 20cost 16 | |
| 9 | Samudayik Bhawan Community Buildings — MORENA(DISTRICT COLLECTOR MORENA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 708 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹10.00 L | HIGH 70
delay 25duplication 20cost 14 | |
| 10 | Samudayik Bhawan Community Buildings — MORENA(DISTRICT COLLECTOR MORENA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 708 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹10.00 L | HIGH 70
delay 25duplication 20cost 14 | |
| 11 | Construction of buildings for community cultural activities Community Buildings — MORENA(DISTRICT COLLECTOR MORENA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 703 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹10.00 L | MEDIUM 70
delay 25duplication 20cost 14 | |
| 12 | COnstruction of COmmunity Hall Community Buildings — MORENA(DISTRICT COLLECTOR MORENA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 703 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹10.00 L | MEDIUM 70
delay 25duplication 20cost 14 | |
| 13 | CC Road Roads & Paving — MORENA(DISTRICT COLLECTOR MORENA_IDA) - ₹1,000,000 against a ₹700,000 median for Roads & Paving works in MORENA (43% above, 104 peer works)
- 704 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹10.00 L | MEDIUM 70
delay 25duplication 20cost 14 | |
| 14 | CC ROAD Roads & Paving — MORENA(DISTRICT COLLECTOR MORENA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 703 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹8.00 L | MEDIUM 69
delay 25duplication 20cost 13 | |
| 15 | CC ROAD Roads & Paving — MORENA(DISTRICT COLLECTOR MORENA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 703 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹6.00 L | MEDIUM 67
delay 25duplication 20cost 11 | |
| 16 | CC ROAD NIRMAN Roads & Paving — MORENA(DISTRICT COLLECTOR MORENA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 708 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹5.30 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 17 | Construction of buildings for community cultural activities Community Buildings — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 703 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹5.00 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 18 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 19 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 20 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 21 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 22 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 23 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 24 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |
| 25 | Purchase of mobile water tankers ( 5500 Lts Tyre Size 900x2 Water — MORENA(DISTRICT COLLECTOR MORENA_IDA) - 715 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 73% delay rate across its projects
| MORENA | ₹1.62 L | MEDIUM 66
delay 25duplication 20agency 11 | |