| 1 | Construction of Dinning and Kitchen room for Sadar Police Community Buildings — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - ₹1,267,200 against a ₹606,900 median for Community Buildings works in WEST SINGHBHUM (109% above, 8 peer works)
- 593 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹12.67 L | MEDIUM 65 | |
| 2 | Installation of 12 mtr High Mask Light at KGBV Chakradharpur Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 601 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹7.40 L | MEDIUM 61 | |
| 3 | Installation of 12 mtr high Mask Light at KGBV Anandpur. Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹7.40 L | MEDIUM 61 | |
| 4 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 61
delay 25agency 15duplication 13 | |
| 5 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 61
delay 25agency 15duplication 13 | |
| 6 | Installation of 12 mtr High Mask Light at KGBV Manoharpur. Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 601 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹7.40 L | MEDIUM 60 | |
| 7 | Installation of 12 mtr high Mask Light at KGBV, Manjhari. Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹7.40 L | MEDIUM 60 | |
| 8 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 97% similarity with another nearby work
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 59
delay 25agency 15duplication 11 | |
| 9 | Installation of 12 mtr High mask Light at KGBV Bandgaon. Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹7.40 L | MEDIUM 58 | |
| 10 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 97% similarity with another nearby work
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 58
delay 25agency 15duplication 10 | |
| 11 | Installation of 12 mtr High Mask Light at Jharkhand Resident Education — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹7.40 L | MEDIUM 58 | |
| 12 | Installation of 12 mtr High Mask light at Jharkhand Resident Education — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹7.40 L | MEDIUM 58 | |
| 13 | Construction of one deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 97% similarity with another nearby work
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 57
delay 25agency 15duplication 9 | |
| 14 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 97% similarity with another nearby work
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 57
delay 25agency 15duplication 9 | |
| 15 | Installation of 16 mtr high mask light at Vill- Patiyar Chow Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.97 L | MEDIUM 57 | |
| 16 | Installation of 16 mtr high mask light at Vill- Pansuan Chow Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.97 L | MEDIUM 56 | |
| 17 | Installation of 16 mtr high mask light at Vill- Sikursai Cho Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.97 L | MEDIUM 56 | |
| 18 | Installation of 16 mtr high mask light at Vill- Mauda Chowk. Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.01 L | MEDIUM 56 | |
| 19 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 96% similarity with another nearby work
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 56
delay 25agency 15duplication 8 | |
| 20 | Installation of 16 mtr high mask Light in Vill- Tonto bazar Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.97 L | MEDIUM 56 | |
| 21 | Installation of 16 mtr high mask light at Vill- Robkera Baza Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.97 L | MEDIUM 56 | |
| 22 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 55 | |
| 23 | Installation of 16 mtr High mask light at Maa Kali Mandir Ch Religious & Cultural — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - ₹896,600 against a ₹555,000 median for Religious & Cultural works in WEST SINGHBHUM (62% above, 9 peer works)
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.97 L | MEDIUM 55 | |
| 24 | Construction of one Deepboring and installation of 2000 ltr Water — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - 602 days beyond expected completion
- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹4.91 L | MEDIUM 55 | |
| 25 | Installation of 16 mtr High mask Light at Vill- san Jhinkpan Street Lighting — WEST SINGHBHUM(DEPUTY COMMISSIONER WEST SINGHBHUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 602 days beyond expected completion
Read more (1 more)Show less- 98% of this agency's ₹76,976,725 spend went to one vendor (HARINANDAN RAJAK JUNIOR ENGINEER NREP W SINGHBHUM CHAIBASA), across 2 vendors and 208 transactions
| WEST SINGHBHUM | ₹8.97 L | MEDIUM 55 | |