| 51 | Construction of sports stadium Sports — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹500,000 against a ₹200,000 median for Sports works in HOSHIARPUR (150% above, 116 peer works)
- 792 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹5.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 52 | Construction of Shamshanghat Religious & Cultural — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in HOSHIARPUR (100% above, 81 peer works)
- 797 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹4.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 53 | Development of sports stadium Sports — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹500,000 against a ₹200,000 median for Sports works in HOSHIARPUR (150% above, 116 peer works)
- 804 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹5.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 54 | For Construction of concrete passage at village malot, Block Roads & Paving — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹1,600,000 against a ₹200,000 median for Roads & Paving works in HOSHIARPUR (700% above, 146 peer works)
- 238 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹16.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 55 | Construction of stadiums Sports — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹1,000,000 against a ₹200,000 median for Sports works in HOSHIARPUR (400% above, 116 peer works)
- 608 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 56 | Construction of Shamshan Ghat Religious & Cultural — HOSHIARPUR(DEPUTY COMMISSIONER HOSHIARPUR_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in HOSHIARPUR (100% above, 81 peer works)
- 358 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HOSHIARPUR | ₹4.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 57 | construction of shelters for animals at shri gopal krishan Community Buildings — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in AMRITSAR (200% above, 63 peer works)
- 220 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹15.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 58 | Various Development work to be carried out on the heritage s Roads & Paving — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹13,402,656 against a ₹485,000 median for Roads & Paving works in AMRITSAR (2663% above, 137 peer works)
- 299 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹1.34 Cr | HIGH 71
cost 25delay 25duplication 20 | |
| 59 | Construction of interlock tiles in govt primary school valla Education — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in AMRITSAR (100% above, 35 peer works)
- 391 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹10.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 60 | Construction of rooms and bathrooms
govt primary school rasu Education — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in AMRITSAR (100% above, 35 peer works)
- 391 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹10.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 61 | construction of shelters for animals at shri gopal krishan Community Buildings — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in AMRITSAR (200% above, 63 peer works)
- 220 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹15.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 62 | Various Development work to be carried out on the heritage s Roads & Paving — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹13,402,656 against a ₹485,000 median for Roads & Paving works in AMRITSAR (2663% above, 137 peer works)
- 299 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹1.34 Cr | HIGH 71
cost 25delay 25duplication 20 | |
| 63 | Construction of interlock tiles in govt primary school valla Education — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in AMRITSAR (100% above, 35 peer works)
- 391 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹10.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 64 | Construction of rooms and bathrooms
govt primary school rasu Education — AMRITSAR(DEPUTY COMMISSIONER AMRITSAR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in AMRITSAR (100% above, 35 peer works)
- 391 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRITSAR | ₹10.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 65 | Laying Pipe Line 18 inch for Disposal of Sullage Water Water — MOGA(Deputy Commissioner Moga) - ₹965,600 against a ₹200,000 median for Water works in MOGA (383% above, 105 peer works)
- 272 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MOGA | ₹9.66 L | HIGH 71
cost 25delay 25duplication 20 | |
| 66 | Laying Pipe Line 18 inch for Disposal of Sullage Water Water — MOGA(Deputy Commissioner Moga) - ₹965,600 against a ₹200,000 median for Water works in MOGA (383% above, 105 peer works)
- 272 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MOGA | ₹9.66 L | HIGH 71
cost 25delay 25duplication 20 | |
| 67 | Installation of Gym Equipment at Mussa(84), Tehsil Mansa Di Sports — MANSA(DEPUTY COMMISSIONER MANSA_IDA) - ₹499,966 against a ₹236,048 median for Sports works in MANSA (112% above, 28 peer works)
- 174 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANSA | ₹5.00 L | HIGH 71
cost 25delay 24duplication 20 | |
| 68 | construction of rooms at anand dham kusht ashram ward no 22 Community Buildings — FEROZEPUR(DEPUTY COMMISSIONER FIROZEPUR_IDA) - ₹2,500,000 against a ₹500,000 median for Community Buildings works in FEROZEPUR (400% above, 40 peer works)
- 218 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FEROZEPUR | ₹25.00 L | HIGH 70
cost 25delay 25duplication 20 | |
| 69 | construction of rooms at anand dham kusht ashram ward no 22 Community Buildings — FEROZEPUR(DEPUTY COMMISSIONER FIROZEPUR_IDA) - ₹2,500,000 against a ₹500,000 median for Community Buildings works in FEROZEPUR (400% above, 40 peer works)
- 218 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| FEROZEPUR | ₹25.00 L | HIGH 70
cost 25delay 25duplication 20 | |
| 70 | const. of cremation centre and streets at vill dhanal kalan Religious & Cultural — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹1,500,000 against a ₹300,000 median for Religious & Cultural works in JALANDHAR (400% above, 51 peer works)
- 73 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹15.00 L | MEDIUM 70
cost 25duplication 20agency 15 | |
| 71 | construction of sports ground Sports — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹2,500,000 against a ₹200,000 median for Sports works in JALANDHAR (1150% above, 153 peer works)
- 73 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹25.00 L | MEDIUM 70
cost 25duplication 20agency 15 | |
| 72 | Construction of Dharamshala Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹350,000 against a ₹200,000 median for Religious & Cultural works in KAPURTHALA (75% above, 17 peer works)
- 659 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹3.50 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 73 | repair/renovation of main block (part-A) ground flour at PHC Health — RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RUPNAGAR | ₹50.00 L | MEDIUM 69
delay 25cost 21duplication 20 | |
| 74 | repair/renovation of main block (part-A) ground flour at PHC Health — RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RUPNAGAR | ₹50.00 L | MEDIUM 69
delay 25cost 21duplication 20 | |
| 75 | Regarding for giving single walled fabrication of 5000ltr wa Water — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - 702 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹3.36 L | MEDIUM 69
delay 25duplication 20agency 15 | |