| 51 | For construction of concrete road at Post office adjacent ro Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (200% above, 257 peer works)
- 738 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹15.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 52 | Development of road work from Sanskrit college to Hosatota c Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (100% above, 257 peer works)
- 738 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 53 | For development of road from Kesagodu to malali at Bilagadhe Roads & Paving — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKAMAGALURU (100% above, 257 peer works)
- 738 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 54 | Banipur Road se Ramswaroop ke khet ke pas Khanba ki aor DevS Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 55 | Jagdish ke khet se Yogendra ki baithak ki aur Dev singh ka p Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 56 | road and nali Roads & Paving — Bara Banki(DISTRICT MAGISTRATE BARABANKI_IDA) - ₹2,383,000 against a ₹1,167,000 median for Roads & Paving works in BARA BANKI (104% above, 35 peer works)
- 213 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 83% of this agency's ₹92,526,962 spend went to one vendor (Praharsh Infrastructure), across 9 vendors and 37 transactions
| BARA BANKI | ₹23.83 L | HIGH 85
cost 25delay 25duplication 20 | |
| 57 | SAARVAJANIKA SAMUDAYA BHAVANA DEVELOPMENT WORK AT KADUR TALU Community Buildings — CHIKKAMAGALURU(DEPUTY COMMISSIONER CHIKMAGALUR) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in CHIKKAMAGALURU (100% above, 108 peer works)
- 220 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹88,040,353 spend went to one vendor (KRIDL BHUSIRI ACCOUNT WORKS), across 27 vendors and 127 transactions
| CHIKKAMAGALURU | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 58 | Laying of RCC Pipeline at Village Birpind, Block Nakodar, Di Water — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹2,500,000 against a ₹365,800 median for Water works in JALANDHAR (583% above, 251 peer works)
- 250 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹25.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 59 | Regarding Construction and repair of Stadium in school. Education — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹1,000,000 against a ₹478,289 median for Education works in JALANDHAR (109% above, 33 peer works)
- 397 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 60 | PANCHAT GHAR Community Buildings — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in JALANDHAR (233% above, 81 peer works)
- 608 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 61 | Construction of community hall in sahilong in dumargadi pan Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹500,000 median for Community Buildings works in KHUNTI (140% above, 30 peer works)
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 62 | This amount of Rs 2,00,00,000 is being released towards the Street Lighting — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹19,933,000 against a ₹174,000 median for Street Lighting works in MUZAFFARNAGAR (11356% above, 33 peer works)
- 189 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹1.99 Cr | HIGH 84
cost 25delay 25duplication 20 | |
| 63 | Construction work of Interlocking Tiles from Main Stand to V Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹2,800,000 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (303% above, 327 peer works)
- 211 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹28.00 L | HIGH 84
cost 25delay 25duplication 20 | |
| 64 | Construction of Interlocking Tiles and Drain from Main Bus S Roads & Paving — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - ₹2,499,400 against a ₹695,000 median for Roads & Paving works in MUZAFFARNAGAR (260% above, 327 peer works)
- 395 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹24.99 L | HIGH 84
cost 25delay 25duplication 20 | |
| 65 | Gram panchayat Ahrolighat, Janpad panchayat Ater ke gram Ahr Community Buildings — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹150,000 against a ₹76,581 median for Community Buildings works in BHIND (96% above, 44 peer works)
- 567 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 84% of this agency's ₹50,485,526 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 29 vendors and 192 transactions
| BHIND | ₹1.50 L | HIGH 84
delay 25cost 24duplication 20 | |
| 66 | Gram panchayat Ahrolighat, Janpad panchayat Ater ke gram Ahr Community Buildings — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹150,000 against a ₹76,581 median for Community Buildings works in BHIND (96% above, 44 peer works)
- 567 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹1.50 L | HIGH 84
delay 25cost 24duplication 20 | |
| 67 | vidhan Sabha Setra Jhadol Phalasia ke Panchayat Samiti Phala Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹2,000,000 against a ₹799,781 median for Education works in UDAIPUR (150% above, 38 peer works)
- 580 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹20.00 L | HIGH 84
cost 25delay 25duplication 19 | |
| 68 | Vidhan Sabha Setra Jhadol Phalasiya ke Panchayat Samiti Kotr Education — UDAIPUR(DISTRICT COLLECTOR UDAIPUR_IDA) - ₹2,000,000 against a ₹799,781 median for Education works in UDAIPUR (150% above, 38 peer works)
- 580 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 763 days
| UDAIPUR | ₹20.00 L | HIGH 84
cost 25delay 25duplication 19 | |
| 69 | Interlocking road 350 mtr Roads & Paving — Sant Kabir Nagar(DISTRICT MAGISTRATE SANT KABIR NAGAR_2) - ₹2,500,000 against a ₹987,924 median for Roads & Paving works in SANT KABIR NAGAR (153% above, 45 peer works)
- 428 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 2 payments still in progress, oldest 674 days
| SANT KABIR NAGAR | ₹25.00 L | HIGH 84
cost 25delay 25duplication 20 | |
| 70 | Construction of Guest House. Community Buildings — Shamator(Deputy Commissioner Shamator_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 646 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 100% delay rate across its projects
| SHAMATOR | ₹1.05 Cr | HIGH 84
delay 25cost 24duplication 20 | |
| 71 | Construction of Guest House. Community Buildings — Shamator(Deputy Commissioner Shamator_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 646 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 100% delay rate across its projects
| SHAMATOR | ₹1.05 Cr | HIGH 84
delay 25cost 24duplication 20 | |
| 72 | Construction of library building Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹10,770,000 against a ₹250,000 median for Education works in VIJAYAPURA (4208% above, 146 peer works)
- 331 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹1.08 Cr | HIGH 83
cost 25delay 25duplication 20 | |
| 73 | Construction of Library Building Education — VIJAYAPURA(DEPUTY COMMISSIONER BIJAPUR_IDA) - ₹8,102,000 against a ₹250,000 median for Education works in VIJAYAPURA (3141% above, 146 peer works)
- 331 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹91,833,067 spend went to one vendor (Nirmithi kendra vijayapur), across 40 vendors and 130 transactions
| VIJAYAPURA | ₹81.02 L | HIGH 83
cost 25delay 25duplication 20 | |
| 74 | Construction of community hall at gram Eklahara, gram Pancha Community Buildings — BETUL(DISTRICT COLLECTOR BETUL_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in BETUL (300% above, 221 peer works)
- 808 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹56,741,127 spend went to one vendor (MP STATE AGRO INDUSTRIES DEVELOPMENT CORP LTD), across 113 vendors and 439 transactions
| BETUL | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 75 | Panchayat Kundalwadah Village Jhitri Pond construction near Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 186 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |