| 26 | Installation of solar street light in durgapur panchayat:
1) Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹176,000 against a ₹22,000 median for Street Lighting works in BOKARO (700% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹1.76 L | HIGH 77
cost 25delay 25duplication 16 | |
| 27 | Construction of a pond in Village-Mankadiha, Badgunda Pancha Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹600,000 against a ₹299,570 median for Water works in GIRIDIH (100% above, 168 peer works)
- 127 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹6.00 L | HIGH 76
cost 25duplication 20delay 18 | |
| 28 | Construction of a guard wall alongside the road in Village-D Roads & Paving — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹600,000 against a ₹300,000 median for Roads & Paving works in GIRIDIH (100% above, 502 peer works)
- 127 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹6.00 L | HIGH 76
cost 25duplication 20delay 18 | |
| 29 | Installation of solar street light in baraikala panchayat:
1 Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹220,000 against a ₹22,000 median for Street Lighting works in BOKARO (900% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹2.20 L | HIGH 76
cost 25delay 25duplication 15 | |
| 30 | Installation of solar street light in baraikala panchayat:
1 Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹198,000 against a ₹22,000 median for Street Lighting works in BOKARO (800% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹1.98 L | HIGH 76
cost 25delay 25duplication 15 | |
| 31 | Construction of boundary wall near aamreshwar dham under tor Boundary & Protection — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹10.00 L | HIGH 76
delay 25duplication 20cost 16 | |
| 32 | Construction of pond in Pannakhurd village under Makhmaargao Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 121 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 75
cost 25duplication 20delay 17 | |
| 33 | Construction of pond in Jogidih village under Jhalakdiha Pan Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 121 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 75
cost 25duplication 20delay 17 | |
| 34 | Panchayat Chapwadiha, Village Fuchcho Pratappur pond - Const Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹500,000 against a ₹299,570 median for Water works in GIRIDIH (67% above, 168 peer works)
- 199 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹5.00 L | HIGH 75
delay 25duplication 20cost 17 | |
| 35 | Panchayat Chapwadiha, Village Nawadih, Adivasi Tola Jharatha Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹500,000 against a ₹299,570 median for Water works in GIRIDIH (67% above, 168 peer works)
- 199 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹5.00 L | HIGH 75
delay 25duplication 20cost 17 | |
| 36 | Construction of a pond in Village-Mankadiha, Badgunda Pancha Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹600,000 against a ₹299,570 median for Water works in GIRIDIH (100% above, 168 peer works)
- 127 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹6.00 L | HIGH 75
cost 25duplication 20delay 18 | |
| 37 | Construction of a guard wall alongside the road in Village-D Roads & Paving — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹600,000 against a ₹300,000 median for Roads & Paving works in GIRIDIH (100% above, 502 peer works)
- 127 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹6.00 L | HIGH 75
cost 25duplication 20delay 18 | |
| 38 | Construction of Community hall(Hostel) for Chota Nagpuria Te Education — GUMLA(DEPUTY COMMISSIONER GUMLA_IDA) - ₹1,449,900 against a ₹400,000 median for Education works in GUMLA (262% above, 66 peer works)
- 105 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 81% of this agency's ₹15,537,973 spend went to one vendor (DE ZP Gumla), across 3 vendors and 34 transactions
| GUMLA | ₹14.50 L | HIGH 75
cost 25duplication 20agency 15 | |
| 39 | Construction of pond in Pannakhurd village under Makhmaargao Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 121 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹10.00 L | HIGH 74
cost 25duplication 20delay 17 | |
| 40 | Construction of pond in Jogidih village under Jhalakdiha Pan Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 121 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹10.00 L | HIGH 74
cost 25duplication 20delay 17 | |
| 41 | Panchayat Chapwadiha, Village Fuchcho Pratappur pond - Const Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹500,000 against a ₹299,570 median for Water works in GIRIDIH (67% above, 168 peer works)
- 199 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹5.00 L | HIGH 74
delay 25duplication 20cost 17 | |
| 42 | Panchayat Chapwadiha, Village Nawadih, Adivasi Tola Jharatha Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹500,000 against a ₹299,570 median for Water works in GIRIDIH (67% above, 168 peer works)
- 199 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹5.00 L | HIGH 74
delay 25duplication 20cost 17 | |
| 43 | Installation of solar street light in taranga panchayat:
1)N Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹220,000 against a ₹22,000 median for Street Lighting works in BOKARO (900% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹2.20 L | HIGH 74
cost 25delay 25duplication 13 | |
| 44 | Installation of solar street light in taranga panchayat:
1)n Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹110,000 against a ₹22,000 median for Street Lighting works in BOKARO (400% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹1.10 L | HIGH 74
cost 25delay 25duplication 13 | |
| 45 | Installation of solar street light in hisim panchayat:
1)Nea Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹220,000 against a ₹22,000 median for Street Lighting works in BOKARO (900% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹2.20 L | HIGH 73
cost 25delay 25duplication 12 | |
| 46 | Installation of solar street light in hisim panchayat:
1)Nea Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹176,000 against a ₹22,000 median for Street Lighting works in BOKARO (700% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹1.76 L | HIGH 73
cost 25delay 25duplication 12 | |
| 47 | Construction of boundary wall in Koka Lagam of panchayat Ban Boundary & Protection — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹1,250,000 against a ₹505,500 median for Boundary & Protection works in RANCHI (147% above, 11 peer works)
- 255 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹12.50 L | HIGH 73
cost 25delay 25duplication 20 | |
| 48 | Construction of boundary wall in Koka Lagam of panchayat Ban Boundary & Protection — RANCHI(DEPUTY COMMISSIONER RANCHI_IDA) - ₹1,250,000 against a ₹505,500 median for Boundary & Protection works in RANCHI (147% above, 11 peer works)
- 255 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RANCHI | ₹12.50 L | HIGH 73
cost 25delay 25duplication 20 | |
| 49 | Installation of solar street light in pachmo panchayat:
1)Ne Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹220,000 against a ₹22,000 median for Street Lighting works in BOKARO (900% above, 443 peer works)
- 344 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹2.20 L | HIGH 73
cost 25delay 25duplication 12 | |
| 50 | Installation of solar street light in pachmo panchayat:
1)Ne Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹220,000 against a ₹22,000 median for Street Lighting works in BOKARO (900% above, 443 peer works)
- 344 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹2.20 L | HIGH 73
cost 25delay 25duplication 12 | |