| 26 | Paving and paver block work in the school ground Roads & Paving — SURAT(DISTRICT COLLECTOR SURAT_IDA) - ₹1,500,000 against a ₹400,000 median for Roads & Paving works in SURAT (275% above, 102 peer works)
- 271 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SURAT | ₹15.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 27 | Paving and paver block work in the school ground Roads & Paving — SURAT(DISTRICT COLLECTOR SURAT_IDA) - ₹1,500,000 against a ₹400,000 median for Roads & Paving works in SURAT (275% above, 102 peer works)
- 271 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SURAT | ₹15.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 28 | Petlad, Ta. Petlad, Dist. Anand: Work on toilet block Near t Drainage & Sanitation — ANAND(District Collector ANAND_IDA) - ₹1,000,000 against a ₹445,405 median for Drainage & Sanitation works in ANAND (125% above, 16 peer works)
- 255 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ANAND | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 29 | Petlad, Ta. Petlad, Dist. Anand: Work on toilet block Near t Drainage & Sanitation — ANAND(District Collector ANAND_IDA) - ₹1,000,000 against a ₹445,405 median for Drainage & Sanitation works in ANAND (125% above, 16 peer works)
- 255 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ANAND | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 30 | Shri Vadgam Taluka Anjana Kelvani Mandal Sanchalit Madhyamik Education — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BANAS KANTHA (100% above, 266 peer works)
- 294 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 31 | Sanadar Ta.Deeodar : Road works next to the lake (2023-24) Roads & Paving — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹1,100,000 against a ₹500,000 median for Roads & Paving works in BANAS KANTHA (120% above, 306 peer works)
- 363 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹11.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 32 | Shri Vadgam Taluka Anjana Kelvani Mandal Sanchalit Madhyamik Education — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BANAS KANTHA (100% above, 266 peer works)
- 294 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 33 | Sanadar Ta.Deeodar : Road works next to the lake (2023-24) Roads & Paving — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹1,100,000 against a ₹500,000 median for Roads & Paving works in BANAS KANTHA (120% above, 306 peer works)
- 363 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹11.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 34 | Vekari Ta.Danta : To build a canteen hall in the tribal ashr Education — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹999,000 against a ₹500,000 median for Education works in BANAS KANTHA (100% above, 266 peer works)
- 363 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹9.99 L | HIGH 71
delay 25cost 25duplication 20 | |
| 35 | Solsanda Ta.Danta : For construction of 2-rooms in Adivasi K Education — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹999,000 against a ₹500,000 median for Education works in BANAS KANTHA (100% above, 266 peer works)
- 363 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹9.99 L | HIGH 71
delay 25cost 25duplication 20 | |
| 36 | Vekari Ta.Danta : To build a canteen hall in the tribal ashr Education — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹999,000 against a ₹500,000 median for Education works in BANAS KANTHA (100% above, 266 peer works)
- 363 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹9.99 L | HIGH 71
delay 25cost 25duplication 20 | |
| 37 | Solsanda Ta.Danta : For construction of 2-rooms in Adivasi K Education — BANAS KANTHA(DISTRICT COLLECTOR BANAS KANTHA_IDA) - ₹999,000 against a ₹500,000 median for Education works in BANAS KANTHA (100% above, 266 peer works)
- 363 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANAS KANTHA | ₹9.99 L | HIGH 71
delay 25cost 25duplication 20 | |
| 38 | Bhimrana Ta.Dist-Devbhumi Dwarka : For road paver work near Roads & Paving — DEVBHUMI DWARKA(DISTRICT COLLECTOR DEVBHUMI DWARKA_IDA) - ₹1,097,700 against a ₹350,000 median for Roads & Paving works in DEVBHUMI DWARKA (214% above, 89 peer works)
- 339 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DEVBHUMI DWARKA | ₹10.98 L | HIGH 71
cost 25delay 25duplication 20 | |
| 39 | Bhimrana Ta.Dist-Devbhumi Dwarka : For road paver work near Roads & Paving — DEVBHUMI DWARKA(DISTRICT COLLECTOR DEVBHUMI DWARKA_IDA) - ₹1,097,700 against a ₹350,000 median for Roads & Paving works in DEVBHUMI DWARKA (214% above, 89 peer works)
- 339 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DEVBHUMI DWARKA | ₹10.98 L | HIGH 71
cost 25delay 25duplication 20 | |
| 40 | of community hall for public purpose Community Buildings — MORBI(District collector Morbi_IDA) - ₹2,320,000 against a ₹510,000 median for Community Buildings works in MORBI (355% above, 142 peer works)
- 261 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MORBI | ₹23.20 L | HIGH 71
cost 25delay 25duplication 20 | |
| 41 | of community hall for public purpose Community Buildings — MORBI(District collector Morbi_IDA) - ₹2,320,000 against a ₹510,000 median for Community Buildings works in MORBI (355% above, 142 peer works)
- 261 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MORBI | ₹23.20 L | HIGH 71
cost 25delay 25duplication 20 | |
| 42 | Dudhrej Ta.Vadhvan Dist.Surendrnagar T.C.U.Shah Medical Coll Education — SURENDRANAGAR(DISTRICT COLLECTOR SURENDRANAGAR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in SURENDRANAGAR (100% above, 25 peer works)
- 339 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SURENDRANAGAR | ₹10.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 43 | Dudhrej Ta.Vadhvan Dist.Surendrnagar T.C.U.Shah Medical Coll Education — SURENDRANAGAR(DISTRICT COLLECTOR SURENDRANAGAR_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in SURENDRANAGAR (100% above, 25 peer works)
- 339 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SURENDRANAGAR | ₹10.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 44 | White tiles Tikdi wala Bankada Roads & Paving — CHHOTAUDEPUR(DISTRICT COLLECTOR CHHOTA UDEPUR_IDA) - ₹2,688,000 against a ₹236,200 median for Roads & Paving works in CHHOTAUDEPUR (1038% above, 179 peer works)
- 174 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHHOTAUDEPUR | ₹26.88 L | HIGH 71
cost 25delay 24duplication 20 | |
| 45 | Construction of Community Hall in Ambedkar Nagar area for Sc Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 46 | For the construction of a cultural hall (community hall) for Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 47 | Construction of Community Hall in Ambedkar Nagar area for Sc Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 48 | For the construction of a cultural hall (community hall) for Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 49 | To establish IPHS mandated Ayushman Arogya Mandir with Solar Religious & Cultural — NARMADA(DISTRICT COLLECTOR NARMADA_IDA) - ₹15,080,100 against a ₹200,000 median for Religious & Cultural works in NARMADA (7440% above, 8 peer works)
- 129 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 54% of this agency's ₹41,850,380 spend went to one vendor (CONNECTWAVE INTEGRATIONS PVT LTD), across 37 vendors and 104 transactions
| NARMADA | ₹1.51 Cr | MEDIUM 69
cost 25duplication 20delay 18 | |
| 50 | Bharat Sevashram Sangh Administered Gurukul Vidhyapeeth For Education — SURAT(DISTRICT COLLECTOR SURAT_IDA) - ₹500,000 against a ₹272,000 median for Education works in SURAT (84% above, 229 peer works)
- 236 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SURAT | ₹5.00 L | MEDIUM 68
delay 25cost 21duplication 20 | |