| 26 | Construction of Building for multi-gym near ABSU office at U Sports — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,500,000 against a ₹1,000,000 median for Sports works in CHIRANG (150% above, 8 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹25.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 27 | construction of road from Kukurmari Market to Namghor, ward Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹3,000,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (275% above, 144 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹30.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 28 | construction of RCC Box Culvert at Anthaiguri(Silguri) villa Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,800,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (125% above, 144 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹18.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 29 | Renovation of administrative Building of Bodosa High School Education — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹3,500,000 against a ₹1,000,000 median for Education works in CHIRANG (250% above, 46 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹35.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 30 | constructionn of Kujia River erosion protection at middle K Boundary & Protection — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹2,000,000 against a ₹1,000,000 median for Boundary & Protection works in CHIRANG (100% above, 25 peer works)
- 451 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹20.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 31 | Construction of protective sheds for preservation of Bhomora Roads & Paving — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 231 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹45.00 L | HIGH 79
delay 25duplication 20cost 19 | |
| 32 | Construction of Road from Natunbasti to Ahom pathar via to d Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in BARPETA (300% above, 143 peer works)
- 365 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹20.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 33 | Construction of road from PWD road to Prodip Das house near Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in BARPETA (140% above, 143 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹12.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 34 | Construction of Road from Natunbasti to Ahom pathar via to d Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in BARPETA (300% above, 143 peer works)
- 365 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹20.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 35 | Construction of road from PWD road to Prodip Das house near Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in BARPETA (140% above, 143 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹12.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 36 | Construction of Open Stage at Jorhat Theatre Hall, Ward No. Community Buildings — JORHAT(DEPUTY COMMISSIONER JORHAT_IDA) - ₹2,500,000 against a ₹250,000 median for Community Buildings works in JORHAT (900% above, 110 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| JORHAT | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 37 | Construction of Community Hall at Bir Pangrao Khetra, Lalimc Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹2,500,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (733% above, 73 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 38 | Construction of Open Stage at Jorhat Theatre Hall, Ward No. Community Buildings — JORHAT(DEPUTY COMMISSIONER JORHAT_IDA) - ₹2,500,000 against a ₹250,000 median for Community Buildings works in JORHAT (900% above, 110 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| JORHAT | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 39 | Construction of Community Hall at Bir Pangrao Khetra, Lalimc Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹2,500,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (733% above, 73 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 40 | Construction of Ganeshguri Krira Aru Sanskritik Yuva Mancha, Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹2,500,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (259% above, 20 peer works)
- 254 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 41 | Construction of New Stage and Green Room at Cheng Ren Campus Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹3,000,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (330% above, 20 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹30.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 42 | Construction of Gym Hall at Abhiruchi Institute of Physical Community Buildings — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹1,500,000 against a ₹600,000 median for Community Buildings works in KAMRUP METRO (150% above, 47 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 43 | Construction of Ganeshguri Krira Aru Sanskritik Yuva Mancha, Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹2,500,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (259% above, 20 peer works)
- 254 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 44 | Construction of New Stage and Green Room at Cheng Ren Campus Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹3,000,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (330% above, 20 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹30.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 45 | Construction of Gym Hall at Abhiruchi Institute of Physical Community Buildings — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹1,500,000 against a ₹600,000 median for Community Buildings works in KAMRUP METRO (150% above, 47 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 46 | Construction of road at Amguri No.1 village under Dangtal VC Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,500,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (88% above, 144 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹15.00 L | HIGH 77
delay 25cost 22duplication 20 | |
| 47 | Construction of RCC Box Culvert at Chota Amguri Village near Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,500,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (88% above, 144 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹15.00 L | HIGH 77
delay 25cost 22duplication 20 | |
| 48 | Construction of Stillway and protection of Chetonaguri irrig Water — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹3,000,000 against a ₹1,600,000 median for Water works in CHIRANG (88% above, 21 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹30.00 L | HIGH 77
delay 25cost 22duplication 20 | |
| 49 | Construction of road at Amguri No.1 village under Dangtal VC Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,500,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (88% above, 144 peer works)
- 448 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹15.00 L | HIGH 77
delay 25cost 22duplication 20 | |
| 50 | Construction of RCC Box Culvert at Chota Amguri Village near Roads & Paving — CHIRANG(Deputy Commissioner Chirang_IDA) - ₹1,500,000 against a ₹800,000 median for Roads & Paving works in CHIRANG (88% above, 144 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 65% delay rate across its projects
| CHIRANG | ₹15.00 L | HIGH 77
delay 25cost 22duplication 20 | |