| 26 | GRAM DEVI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - Completed work has no photographic documentation on record
- ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 45
cost 25agency 15compliance 5 | |
| 27 | COMPOUND OTHERS WORK Boundary & Protection — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 44 | |
| 28 | ITAGI BHIMAMBIKA BHOJANALAYA Religious & Cultural — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 44 | |
| 29 | construction of veerabhadreshwar sabha bhavan Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 44
cost 25agency 15duplication 4 | |
| 30 | continued construction of Shri veerabhadreshwar sabha bhavan Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 44
cost 25agency 15duplication 4 | |
| 31 | VAIRAGYA NIDHI AKKA MAHADEVI SANGHA Other — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 191 days beyond expected completion
- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | MEDIUM 42 | |
| 32 | Tripuranteshwar Sabha Bhavan Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 42 | |
| 33 | karnataka sanghad ranga mandir Religious & Cultural — MANDYA(DEPUTY COMMISSIONER MANDYA_IDA) - 128 days beyond expected completion
- 90% of this agency's ₹44,437,263 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA MANDYA), across 4 vendors and 119 transactions
| MANDYA | ₹10.00 L | MEDIUM 41 | |
| 34 | SANGAMESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 41 | |
| 35 | SHARAN BASAVESHWAR KALYAN MANTAP Religious & Cultural — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 41 | |
| 36 | AMBEDKAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 41 | |
| 37 | ADI KAVI MAHARSHI VALMIKI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 41 | |
| 38 | Construction of Banajigar Sabha bhavan Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |
| 39 | CONSTRUCTION OF CONTINUED KRUTAPUR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |
| 40 | CONTINUED CONSTRUCTION OF PANCHA CHARYA PANCHAMASALI SEVA KE Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |
| 41 | CONSTRUCTION OF RAITHA SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |
| 42 | Construction of Shambulingeshwar Sabhabhavan Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |
| 43 | BANAJIGAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |
| 44 | TAPCMS BUILDING CONSTRUCTION Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |
| 45 | CONSTRUCTION OF VIRASHAIV PANCHACHARYA VIDYAVARDAK AND SAMSK Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 40 | |