| 1 | Construction of Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 95 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 66
cost 25duplication 20delay 13 | |
| 2 | Construction of Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 88 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 65
cost 25duplication 20delay 12 | |
| 3 | Construction of Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,500,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (186% above, 55 peer works)
- 86 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹15.00 L | MEDIUM 65
cost 25duplication 20delay 12 | |
| 4 | Construction of Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 82 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 64
cost 25duplication 20delay 11 | |
| 5 | Construction of Dr B R Ambedkar Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,294,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (146% above, 55 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.94 L | MEDIUM 61
cost 25duplication 20delay 8 | |
| 6 | construction of Iron/Tin shed in Ambedkar Bhawan Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - 289 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹4.00 L | MEDIUM 58
delay 25duplication 16cost 8 | |
| 7 | construction of Iron/Tin shed in Ambedkar Bhawan (SC) Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - 289 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹2.00 L | MEDIUM 57
delay 25duplication 16cost 8 | |
| 8 | CONSTRUCTION OF HALL ON PANCHAYTI LAND NEAR GURUDWARA Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,000,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (90% above, 55 peer works)
- 596 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹10.00 L | MEDIUM 55 | |
| 9 | Construction of Ambedkar Bhawan & Boundry walls (SC) Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,000,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (90% above, 55 peer works)
- 658 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹10.00 L | MEDIUM 55 | |
| 10 | Completion of SC Choupal Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 55
cost 25duplication 20agency 8 | |
| 11 | Construction of Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,400,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (167% above, 55 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹14.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 12 | Construction of Dr B R Ambedkar Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,400,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (167% above, 55 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹14.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 13 | Construction of Hall Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,300,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (148% above, 55 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹13.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 14 | CONSTRUCTION OF HALL Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 15 | Construction of Shed Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,000,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (90% above, 55 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹10.00 L | MEDIUM 53
cost 23duplication 20agency 8 | |
| 16 | Construction of General Choupal in Village Machhrauli Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 118 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 49 | |
| 17 | Construction of Dr. B.R. Ambekdar Hall in village Milk Sukhi Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 118 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 49 | |
| 18 | Completion of SC choupal Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - 95 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹2.11 L | MEDIUM 46
duplication 20delay 13agency 8 | |
| 19 | Construction of SC choupal Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,200,000 against a ₹525,000 median for Community Buildings works in YAMUNANAGAR (129% above, 55 peer works)
- 95 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹12.00 L | MEDIUM 46 | |
| 20 | construction of lane and drain from the house of Surjeet Sin Drainage & Sanitation — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹1,000,000 against a ₹375,000 median for Drainage & Sanitation works in YAMUNANAGAR (167% above, 12 peer works)
- 93 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹10.00 L | MEDIUM 46 | |
| 21 | construction of shed Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - 86 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹4.00 L | MEDIUM 46
duplication 20delay 12agency 8 | |
| 22 | 1.Construction of IPB Street from Anganwadi centre towards S Roads & Paving — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹500,000 against a ₹350,000 median for Roads & Paving works in YAMUNANAGAR (43% above, 29 peer works)
- 602 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹5.00 L | MEDIUM 44 | |
| 23 | Construction of lane from firni to the house of Sh Pahal Sin Roads & Paving — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - ₹900,000 against a ₹350,000 median for Roads & Paving works in YAMUNANAGAR (157% above, 29 peer works)
- 74 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹9.00 L | MEDIUM 43 | |
| 24 | CONSTRUCTION OF HALL NEAR GRAM SACHIVALYA Community Buildings — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - 596 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹6.00 L | MEDIUM 42 | |
| 25 | Construction of hall, boundry wall, kitchen and toilets in A Drainage & Sanitation — YAMUNANAGAR(Deputy Commissioner YamunaNagar_IDA) - 658 days beyond expected completion
- Implementing agency has a 52% delay rate across its projects
| YAMUNANAGAR | ₹5.00 L | MEDIUM 42 | |