| 1 | Construction of Culvert and Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹499,765 median for Roads & Paving works in TUMAKURU (100% above, 215 peer works)
- 321 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | Construction of Community Hall at Brammasandra Village, Kall Community Buildings — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in TUMAKURU (100% above, 149 peer works)
- 339 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | CC Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹2,000,000 against a ₹499,765 median for Roads & Paving works in TUMAKURU (300% above, 215 peer works)
- 550 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹20.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | Continuation Construction of Community Hall Community Buildings — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in TUMAKURU (100% above, 149 peer works)
- 550 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Construction of Community Hall Community Buildings — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in TUMAKURU (100% above, 149 peer works)
- 550 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 6 | Construction of Community Hall Community Buildings — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in TUMAKURU (100% above, 149 peer works)
- 550 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 7 | Construction of Culvert and Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹499,765 median for Roads & Paving works in TUMAKURU (100% above, 215 peer works)
- 321 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| TUMAKURU | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 8 | Construction of Community Hall at Brammasandra Village, Kall Community Buildings — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in TUMAKURU (100% above, 149 peer works)
- 339 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| TUMAKURU | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 9 | Development of Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹800,000 against a ₹499,765 median for Roads & Paving works in TUMAKURU (60% above, 215 peer works)
- 550 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹8.00 L | MEDIUM 67
delay 25duplication 20cost 15 | |
| 10 | Construction of Community Hall Community Buildings — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹800,000 against a ₹500,000 median for Community Buildings works in TUMAKURU (60% above, 149 peer works)
- 550 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹8.00 L | MEDIUM 67
delay 25duplication 20cost 15 | |
| 11 | Construction of Cement Concrete Road (C C Road) from Prakash Street Lighting — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹500,000 against a ₹299,000 median for Street Lighting works in TUMAKURU (67% above, 89 peer works)
- 142 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹5.00 L | MEDIUM 63
duplication 20delay 20cost 17 | |
| 12 | Construction of Cement Concrete Road (C C Road) from Prakash Street Lighting — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹500,000 against a ₹299,000 median for Street Lighting works in TUMAKURU (67% above, 89 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| TUMAKURU | ₹5.00 L | MEDIUM 62
duplication 20delay 20cost 17 | |
| 13 | construction of shivayogishwara hostel at turuvekere town, T Education — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹2,500,000 against a ₹742,087 median for Education works in TUMAKURU (237% above, 42 peer works)
- 75 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹25.00 L | MEDIUM 62
cost 25duplication 20delay 10 | |
| 14 | construction of shivayogishwara hostel at turuvekere town, T Education — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹2,500,000 against a ₹742,087 median for Education works in TUMAKURU (237% above, 42 peer works)
- 75 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| TUMAKURU | ₹25.00 L | MEDIUM 61
cost 25duplication 20delay 10 | |
| 15 | Construction of Bridge near Mayanna's Thota, Jadiya village, Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 417 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 16 | Construction of Barrier, Mayasandra Village, Mayasandra Gram Boundary & Protection — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 414 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 17 | CC Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 18 | Repair of School Building Education — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 19 | CC Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 20 | CC Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 21 | CC Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 22 | CC Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 23 | Development of Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 24 | Development of Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 25 | Development of Road Roads & Paving — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - 550 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |