| 1 | CONSTRUTION OF COMUNNITY HALL AT ANTARDA UNDER TARBHA NAC Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹600,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (200% above, 139 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹6.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | Construction of Community Centre at Village Sukhlasar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | Construction of Community Centre at Village Ainlapali Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 4 | CONSTRUTION OF COMUNNITY HALL AT ANTARDA UNDER TARBHA NAC Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹600,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (200% above, 139 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹6.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 5 | Construction of Community Centre at Village Sukhlasar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 6 | Construction of Community Centre at Village Ainlapali Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 7 | Const. of CC Building at Ward No.15 Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 60
delay 25duplication 14cost 13 | |
| 8 | Const. of CC at Dumal Samaj Maheswari Bhaban at Janmura Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (150% above, 139 peer works)
- 692 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 59 | |
| 9 | Const. of CC at Kaibarta Samaj at Sonepur Municipality Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (150% above, 139 peer works)
- 692 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 59 | |
| 10 | Construction of Kalyan Mandap at village- Dhatukipali, GP- G Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - ₹1,000,000 against a ₹250,000 median for Religious & Cultural works in SUBARNAPUR (300% above, 30 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹10.00 L | MEDIUM 54
cost 25duplication 20agency 9 | |
| 11 | Construction of Kalyan Mandap at village- Dhatukipali, GP- G Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - ₹1,000,000 against a ₹250,000 median for Religious & Cultural works in SUBARNAPUR (300% above, 30 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹10.00 L | MEDIUM 54
cost 25duplication 20agency 9 | |
| 12 | Construction of Community Centre near Yogasala in MAHADA Gra Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (150% above, 139 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 54
cost 25duplication 20agency 9 | |
| 13 | Construction of Community Centre near Yogasala in MAHADA Gra Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (150% above, 139 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 54
cost 25duplication 20agency 9 | |
| 14 | Construction of Meeting Hall at Saraswasti Shishu Vidya Mand Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹1,000,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (400% above, 139 peer works)
- 101 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹10.00 L | MEDIUM 48 | |
| 15 | Construction of Additional Classroom in Saraswati Shishu Vid Education — Subarnapur(District Collector Subarnapur_IDA) - ₹500,000 against a ₹300,000 median for Education works in SUBARNAPUR (67% above, 20 peer works)
- 101 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹5.00 L | MEDIUM 48 | |
| 16 | Const. of CC Building near Hanuman Mandir at Bagbar Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹1.00 L | MEDIUM 47 | |
| 17 | Const. of CC Building near Maheshwari Mandir at Phulmuthi, C Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 18 | Const. of CC building near Purnamsi Sankrutika Sansad at Kar Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 19 | Const. of CC Building at Andhradera near Metakani Mandir at Religious & Cultural — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 20 | Const. of CC Building at Kuhibahal Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 21 | Const. of CC Building at Tulundapali, Seledi GP Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 22 | Const. of CC Building at Kaudiamunda, Sankara GP Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 23 | Const. of CC Building at Khemaloi Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 24 | Const. of CC Building at Kumarkeli,GP-Mahada Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |
| 25 | Const. of CC Building at Kadodar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 775 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹2.00 L | MEDIUM 47 | |