| 1 | Construction of Community Hall at Bir Pangrao Khetra, Lalimc Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹2,500,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (733% above, 73 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | Construction of Community Hall at Bir Pangrao Khetra, Lalimc Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹2,500,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (733% above, 73 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | CONSTRUCTION OF LAKSHMIJAN BAGISA RANGAMANCHA, ADPURIA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | CONSTRUCTION OF OFFICE BUILDING OF GAON PRADHAN NAZIRA, WARD Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹1,200,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (300% above, 73 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | CONSTRUCTION OF BAULIPUKHURI RANGAMANCHA, SENCHOA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 6 | CONSTRUCTION OF LALIM CHAPORI BAGHJAN JARADHARA RANGA MANCHA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 7 | CONSTRUCTION OF DEHINGIA GAON CULTRUAL CENTRE, KUKURACHUWA N Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 8 | DEVELOPMENT OF TIPHOK SAH BAGISA RANGAMANCHA, TIPHOK GRANT Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 9 | CONSTRUCTION OF MATHURAPUR RATION GARDEN FIELD RANGAMANCHA, Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 10 | CONSTRUCTION OF SANTIPUR RANGAMANCHA, 6 NO BAKUPUKHURI HABI Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 11 | DEVELOPMENT OF BIHUBOR CHAT PUJA GHAT, GARMUR MIRI Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 12 | CONSTRUCTION OF GELEKY MODI NAGAR RANGA MANCHA, ATHKHEL GRAN Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 13 | CONSTRUCTION OF NA-PAM BARUATI KOLIYAPANI RANGA MANCHA, DEOP Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 14 | CONSTRUCTION OF GAHORICHUA BARI SANG GHARIA CHUK CULTURAL CE Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 15 | CONSTRUCTION OF BORMISING RANGA MANCHA, SANTAK BORMICHING Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹1,000,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (302% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 16 | CONSTRUCTION OF TALL MISING RANGA MANCHA, BALIMIRI Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 17 | CONSTRUCTION OF 22 NO UPAR NAMSAI RANGA MANCHA, 46 NO UPPER Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 18 | CONSTRUCTION OF LIGIRIPUKHURI SANGASKRITIK BIKASH KENDRA, HA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 19 | DEVELOPMENT OF BORUAH ALI NAPUKHURI RANGA MANCHA, NAMTI BANG Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹500,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (101% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 20 | DEVELOPMENT OF BOSASAYAK DIBRUWAL GAON CULTURAL CENTRE, BOSA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹500,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (101% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 21 | DEVELOPMENT OF BAGHJAN BAGAN RANGA MANCHA, BAGHJAN GRANT Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹500,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (101% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 22 | CONSTRUCTION OF DHOLE BAGAN TEA TRIBE CULTURAL CENTRE, BAKUP Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹500,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (101% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 23 | CONSTRUCTION OF BANTUNG CHANDI TALA MUKOLI MANCHA, BELENGBAR Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹500,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (101% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 24 | DEVELOPMENT OF SANTAK ANCHALIK SARBAJANIN SAMSAN GHAT, BOGDA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹500,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (101% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 25 | DEVELOPMENT OF BAMUN PUKHURI BAGISA RANGA MANCHA, BAMUNPUKHU Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹500,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (101% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |