| 1 | Construction of Rest House and Tin Shed in Aam Chowk Muslim Community Buildings — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹853,212 median for Community Buildings works in SIKAR (76% above, 26 peer works)
- 201 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 66
delay 25duplication 20cost 19 | |
| 2 | Construction of Rest House and Tin Shed in Aam Chowk Muslim Community Buildings — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹853,212 median for Community Buildings works in SIKAR (76% above, 26 peer works)
- 201 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 66
delay 25duplication 20cost 19 | |
| 3 | Shavdaah Tinshed Nirman Kary, Shamshaan Ghat, Shyampura, GP Religious & Cultural — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹597,832 median for Religious & Cultural works in SIKAR (151% above, 13 peer works)
- 121 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 64
cost 25duplication 20delay 17 | |
| 4 | Shavdaah Tinshed Nirman Kary, Shamshaan Ghat, Shyampura, GP Religious & Cultural — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹597,832 median for Religious & Cultural works in SIKAR (151% above, 13 peer works)
- 121 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 64
cost 25duplication 20delay 17 | |
| 5 | 1- For construction work of community building and park near Sports — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹1,040,864 median for Sports works in SIKAR (44% above, 12 peer works)
- 377 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 6 | 1- For construction work of community building and park near Sports — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹1,040,864 median for Sports works in SIKAR (44% above, 12 peer works)
- 377 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 7 | For the construction work of interlock with basketball ball Sports — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹1,040,864 median for Sports works in SIKAR (44% above, 12 peer works)
- 328 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 8 | For the construction work of interlock with basketball ball Sports — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹1,040,864 median for Sports works in SIKAR (44% above, 12 peer works)
- 328 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 9 | Construction of boundary wall of Government Higher Secondary Education — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹999,907 against a ₹600,000 median for Education works in SIKAR (67% above, 83 peer works)
- 118 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹10.00 L | MEDIUM 55
duplication 20cost 17delay 16 | |
| 10 | Construction of boundary wall of Government Higher Secondary Education — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹999,907 against a ₹600,000 median for Education works in SIKAR (67% above, 83 peer works)
- 118 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹10.00 L | MEDIUM 55
duplication 20cost 17delay 16 | |
| 11 | SOLAR PANEL INSTALLATION IN GOVT HIGH SCHOOL, VILLAGE SOLA Education — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - 255 days beyond expected completion
- 100% similarity with another nearby work
| SIKAR | ₹5.00 L | MEDIUM 55
delay 25duplication 20cost 8 | |
| 12 | SOLAR PANEL INSTALLATION IN GOVT HIGH SCHOOL, VILLAGE SOLA Education — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - 255 days beyond expected completion
- 100% similarity with another nearby work
| SIKAR | ₹5.00 L | MEDIUM 55
delay 25duplication 20cost 8 | |
| 13 | Construcction work of classroom and verandha Govt Sr Sec Sch Education — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - ₹1,500,000 against a ₹600,000 median for Education works in SIKAR (150% above, 83 peer works)
- 201 days beyond expected completion
| SIKAR | ₹15.00 L | MEDIUM 52 | |
| 14 | CC Block Development work from Jhabarmal' House to Tormal Sh Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,996,014 against a ₹599,958 median for Roads & Paving works in SIKAR (233% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹19.96 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 15 | 6 TOILETS ON FIRST FLOOR AND 6 TOILETS ON GROUND FLOOR DEVEL Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,498,732 against a ₹599,958 median for Roads & Paving works in SIKAR (150% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.99 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 16 | SAGARMAL GURJAR KE GHAR SE PRAMESHWAR GURJAR KE GHAR KI TARF Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,423,422 against a ₹599,958 median for Roads & Paving works in SIKAR (137% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.23 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 17 | CC BLOCK ROAD DEVELOPMENT WORK FROM RATAN MALI'S HOUSE TO GO Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,499,362 against a ₹599,958 median for Roads & Paving works in SIKAR (150% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.99 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 18 | CC BLOCK ROAD DEVELOPMENT FROM MAIN ROAD TO BANWARI DHUKALRA Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,470,105 against a ₹599,958 median for Roads & Paving works in SIKAR (145% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.70 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 19 | Construction of Interlock from Main Road to Surendra Singh H Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,500,000 against a ₹599,958 median for Roads & Paving works in SIKAR (150% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 20 | CC Block Development work from Jhabarmal' House to Tormal Sh Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,996,014 against a ₹599,958 median for Roads & Paving works in SIKAR (233% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹19.96 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 21 | 6 TOILETS ON FIRST FLOOR AND 6 TOILETS ON GROUND FLOOR DEVEL Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,498,732 against a ₹599,958 median for Roads & Paving works in SIKAR (150% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.99 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 22 | SAGARMAL GURJAR KE GHAR SE PRAMESHWAR GURJAR KE GHAR KI TARF Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,423,422 against a ₹599,958 median for Roads & Paving works in SIKAR (137% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.23 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 23 | CC BLOCK ROAD DEVELOPMENT WORK FROM RATAN MALI'S HOUSE TO GO Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,499,362 against a ₹599,958 median for Roads & Paving works in SIKAR (150% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.99 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 24 | CC BLOCK ROAD DEVELOPMENT FROM MAIN ROAD TO BANWARI DHUKALRA Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,470,105 against a ₹599,958 median for Roads & Paving works in SIKAR (145% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹14.70 L | MEDIUM 52
cost 25duplication 20compliance 5 | |
| 25 | Construction of Interlock from Main Road to Surendra Singh H Roads & Paving — SIKAR(DISTRICT COLLECTOR SIKAR_IDA) - Completed work has no photographic documentation on record
- ₹1,500,000 against a ₹599,958 median for Roads & Paving works in SIKAR (150% above, 130 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| SIKAR | ₹15.00 L | MEDIUM 52
cost 25duplication 20compliance 5 | |