| 1 | Construction of Resource Room (Single Storey) 2 Nos. (Part-A Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹50.00 L | HIGH 72
cost 25delay 25duplication 19 | |
| 2 | Construction of Resource Room (Single Storey) 2 Nos. (Part-B Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹50.00 L | HIGH 72
cost 25delay 25duplication 19 | |
| 3 | Construction of Courtyard Shade (Part-A) at Amnour Vishwa Pr Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹50.00 L | HIGH 72
cost 25delay 25duplication 19 | |
| 4 | Construction of Courtyard Shade (Part-B) at Amnour Vishwa Pr Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹50.00 L | HIGH 72
cost 25delay 25duplication 19 | |
| 5 | Construction of 3 Unit Food Court (Part-A) at Amrit Sarovar, Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹4,700,000 against a ₹1,427,198 median for Community Buildings works in SARAN (229% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹47.00 L | HIGH 72
cost 25delay 25duplication 19 | |
| 6 | Construction of 3 Unit Food Court (Part-B) at Amrit Sarovar, Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹4,692,567 against a ₹1,427,198 median for Community Buildings works in SARAN (229% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹46.93 L | HIGH 72
cost 25delay 25duplication 19 | |
| 7 | Construction of Courtyard Shade (Part-C) at Amnour Vishwa Pr Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹50.00 L | HIGH 71
cost 25delay 25duplication 19 | |
| 8 | Construction of 3 Unit Food Court (Part-C) at Amrit Sarovar, Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹50.00 L | HIGH 71
cost 25delay 25duplication 18 | |
| 9 | Construction of 3 Unit Food Court (Part-D) at Amrit Sarovar, Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| SARAN | ₹50.00 L | HIGH 71
cost 25delay 25duplication 18 | |
| 10 | Construction of Outdoor Gym in 8 locations in Various Blocks Sports — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹7,176,000 against a ₹1,710,000 median for Sports works in SARAN (320% above, 9 peer works)
- 564 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| SARAN | ₹71.76 L | MEDIUM 69
cost 25delay 25duplication 16 | |
| 11 | Construction of Outdoor Gym in 70 locations in Various Block Sports — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹65,000,000 against a ₹1,710,000 median for Sports works in SARAN (3701% above, 9 peer works)
- 599 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| SARAN | ₹6.50 Cr | MEDIUM 69
cost 25delay 25duplication 16 | |
| 12 | Construction work of ten additional rooms and two toilets (i Water — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 313 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹59.91 L | MEDIUM 68
delay 25cost 20duplication 20 | |
| 13 | Construction work of ten additional rooms and two toilets (i Water — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 313 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARAN | ₹59.91 L | MEDIUM 68
delay 25cost 20duplication 20 | |
| 14 | Construction of Resource Room (Double Storey) at Amnour Vish Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
Read more (1 more)Show less- 97% similarity with another nearby work
| SARAN | ₹50.00 L | MEDIUM 64
cost 25delay 25duplication 11 | |
| 15 | Construction of Toilet on the East side at Amnour Pokhara, A Drainage & Sanitation — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 702 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| SARAN | ₹15.00 L | MEDIUM 60
delay 25duplication 16cost 16 | |
| 16 | Construction of Toilet on the West side at Amnour Pokhara, A Drainage & Sanitation — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 702 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| SARAN | ₹15.00 L | MEDIUM 60
delay 25duplication 16cost 16 | |
| 17 | Construction of Room on the West Side at Amrit Sarovar, Amno Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 581 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| SARAN | ₹12.56 L | MEDIUM 57
delay 25duplication 15cost 14 | |
| 18 | Construction of Drainage Work, Landscaping, Community Kitche Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
| SARAN | ₹50.00 L | MEDIUM 53 | |
| 19 | Construction of Dining Block at Amnour Vishwa Prabha Communi Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹5,000,000 against a ₹1,427,198 median for Community Buildings works in SARAN (250% above, 51 peer works)
- 581 days beyond expected completion
| SARAN | ₹50.00 L | MEDIUM 53 | |
| 20 | Construction of Room on the East Side at Amrit Sarovar, Amno Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - 581 days beyond expected completion
- 98% similarity with another nearby work
| SARAN | ₹5.50 L | MEDIUM 51
delay 25duplication 15cost 9 | |
| 21 | Works of Crown Jet Fountain & Electrification and PHE Works Sports — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - ₹2,700,000 against a ₹1,710,000 median for Sports works in SARAN (58% above, 9 peer works)
- 576 days beyond expected completion
| SARAN | ₹27.00 L | MEDIUM 46 | |
| 22 | To construct Resource Person Room, Kitchen and Toilet on the Drainage & Sanitation — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 769 days beyond expected completion
| SARAN | ₹15.00 L | MEDIUM 45 | |
| 23 | Construction of public use room and Pantry behind the main b Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 769 days beyond expected completion
| SARAN | ₹15.00 L | MEDIUM 45 | |
| 24 | Construction of additional room and Toilet for Vikas Bhawan Drainage & Sanitation — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 751 days beyond expected completion
| SARAN | ₹11.87 L | MEDIUM 44 | |
| 25 | Gram Gandar Me Khata NO. 128, Sarve No. 104 Par Samudayik Bh Community Buildings — SARAN(DISTRICT PLANNING OFFICE SARAN CHAPRA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 724 days beyond expected completion
| SARAN | ₹11.44 L | MEDIUM 43 | |