| 1 | Construction of shed Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,500,000 against a ₹598,857 median for Community Buildings works in RAIGARH (150% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | construction of community hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 69
delay 25duplication 20cost 17 | |
| 3 | Construction of community hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 69
delay 25duplication 20cost 17 | |
| 4 | Construction of Community hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 69
delay 25duplication 20cost 17 | |
| 5 | Construction of Community building Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹2,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (234% above, 37 peer works)
- 113 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹20.00 L | MEDIUM 68
cost 25duplication 20delay 16 | |
| 6 | construction of community Hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹7.00 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 7 | Construction of Community Hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹7.00 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 8 | construction of shed Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹1.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 9 | construction of cultural stage Religious & Cultural — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹1.50 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 10 | Construction Of Community Hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 11 | Construction of Community hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 12 | Construction of Community Hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 13 | Construction of Cultural Stage Religious & Cultural — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹2.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 14 | Construction of cultural stage Religious & Cultural — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹2.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 15 | construction of cultural stage Religious & Cultural — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹2.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 16 | Construction of cultural stage Religious & Cultural — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹2.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 17 | construction of shed Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - 310 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹3.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 18 | Construction of Community Building Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 90 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 56
duplication 20cost 17delay 13 | |
| 19 | Construction of Community Building Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 90 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 56
duplication 20cost 17delay 13 | |
| 20 | Subhas Pradhan Ghar se Nehru Talab Bargad Ped tak 500 Meter Water — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹600,000 against a ₹225,000 median for Water works in RAIGARH (167% above, 8 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹6.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 21 | Construction of community hall Near Samleshwari Mandir MOTI Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹3,500,000 against a ₹598,857 median for Community Buildings works in RAIGARH (484% above, 37 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹35.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 22 | Subhas Pradhan Ghar se Nehru Talab Bargad Ped tak 500 Meter Water — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹600,000 against a ₹225,000 median for Water works in RAIGARH (167% above, 8 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹6.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 23 | Construction of community hall Near Samleshwari Mandir MOTI Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹3,500,000 against a ₹598,857 median for Community Buildings works in RAIGARH (484% above, 37 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹35.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 24 | Construction of communitiy hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 49 | |
| 25 | Construction of community hall on the existing Community bui Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 49 | |