| 1 | construction work of 250 mtr cc road from mr. subhash mishr Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,180,000 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (170% above, 370 peer works)
- 244 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹11.80 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | In Pure Chauhan village of Sadwa Chandika development block Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,035,000 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (137% above, 370 peer works)
- 319 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹10.35 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | Construction of Classrooms & Laboratory at Gandhi Inter Coll Education — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹2,000,000 against a ₹80,400 median for Education works in PRATAPGARH (2388% above, 216 peer works)
- 339 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹20.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹508,000 against a ₹50,800 median for Water works in PRATAPGARH (900% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.08 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹558,800 against a ₹50,800 median for Water works in PRATAPGARH (1000% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.59 L | HIGH 77
cost 25delay 25duplication 20 | |
| 6 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹406,400 against a ₹50,800 median for Water works in PRATAPGARH (700% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹4.06 L | HIGH 77
cost 25delay 25duplication 20 | |
| 7 | construction work of 250 mtr cc road from mr. subhash mishr Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,180,000 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (170% above, 370 peer works)
- 244 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹11.80 L | HIGH 77
cost 25delay 25duplication 20 | |
| 8 | In Pure Chauhan village of Sadwa Chandika development block Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,035,000 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (137% above, 370 peer works)
- 319 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹10.35 L | HIGH 77
cost 25delay 25duplication 20 | |
| 9 | Construction of Classrooms & Laboratory at Gandhi Inter Coll Education — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹2,000,000 against a ₹80,400 median for Education works in PRATAPGARH (2388% above, 216 peer works)
- 339 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹20.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 10 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹508,000 against a ₹50,800 median for Water works in PRATAPGARH (900% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.08 L | HIGH 77
cost 25delay 25duplication 20 | |
| 11 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹558,800 against a ₹50,800 median for Water works in PRATAPGARH (1000% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹5.59 L | HIGH 77
cost 25delay 25duplication 20 | |
| 12 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹406,400 against a ₹50,800 median for Water works in PRATAPGARH (700% above, 445 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹4.06 L | HIGH 77
cost 25delay 25duplication 20 | |
| 13 | Vikashkhand Shivgarh Gram Audhanpur Me Arvind Panday (Rinku) Street Lighting — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 736 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹1.26 L | MEDIUM 63
delay 25duplication 20cost 11 | |
| 14 | Vikashkhand Shivgarh Gram Audhanpur Me Arvind Panday (Rinku) Street Lighting — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 736 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹1.26 L | MEDIUM 63
delay 25duplication 20cost 11 | |
| 15 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 16 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 17 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 18 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 19 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 20 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 21 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 22 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 23 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 24 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |
| 25 | Installation of Handpumps at Raki, Mustafabad, Narwal, Usman Water — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹50,800 | MEDIUM 62
delay 25duplication 20cost 11 | |