| 1 | Legislative Assembly- Rampur Khas, Tehsil- Lalganj, District Street Lighting — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹962,576 against a ₹185,858 median for Street Lighting works in PRATAPGARH (418% above, 586 peer works)
- 601 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹9.63 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | Construction of CC Road near the temple from CC Road in Baba Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,226,037 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (181% above, 370 peer works)
- 623 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹12.26 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | Legislative Assembly- Rampur Khas, Tehsil- Lalganj, District Street Lighting — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹962,576 against a ₹185,858 median for Street Lighting works in PRATAPGARH (418% above, 586 peer works)
- 601 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹9.63 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | Construction of CC Road near the temple from CC Road in Baba Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,226,037 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (181% above, 370 peer works)
- 623 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹12.26 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | CC road construction work
(CC road work from Hikaya's house Roads & Paving — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹1,000,000 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (129% above, 370 peer works)
- 343 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PRATAPGARH | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 6 | CC road construction work
(CC road work from Hikaya's house Roads & Paving — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹1,000,000 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (129% above, 370 peer works)
- 343 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PRATAPGARH | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 7 | For construction of building for cultural activities near Ma Religious & Cultural — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - 376 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹2.50 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 8 | For construction of building for cultural activities near Ma Religious & Cultural — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - 376 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹2.50 L | MEDIUM 60
delay 25duplication 20cost 8 | |
| 9 | Government Higher Primary School Jambukheda Classroom One Education — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹1,000,000 against a ₹80,400 median for Education works in PRATAPGARH (1144% above, 216 peer works)
- 92 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PRATAPGARH | ₹10.00 L | MEDIUM 60
cost 25duplication 20delay 13 | |
| 10 | Government Higher Primary School Jambukheda Classroom One Education — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹1,000,000 against a ₹80,400 median for Education works in PRATAPGARH (1144% above, 216 peer works)
- 92 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PRATAPGARH | ₹10.00 L | MEDIUM 60
cost 25duplication 20delay 13 | |
| 11 | For the construction of two additional rooms in the hostel o Education — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹2,500,000 against a ₹80,400 median for Education works in PRATAPGARH (3009% above, 216 peer works)
- 100% similarity with another nearby work
| PRATAPGARH | ₹25.00 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 12 | For the construction of two additional rooms in the hostel o Education — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹2,500,000 against a ₹80,400 median for Education works in PRATAPGARH (3009% above, 216 peer works)
- 100% similarity with another nearby work
| PRATAPGARH | ₹25.00 L | MEDIUM 55
cost 25duplication 20delay 8 | |
| 13 | SARVJANIKA KUPA NIRAMN KATYA BADLI KHARI (SEMALAKHESI) Water — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹400,000 against a ₹50,800 median for Water works in PRATAPGARH (687% above, 445 peer works)
- 559 days beyond expected completion
| PRATAPGARH | ₹4.00 L | MEDIUM 52 | |
| 14 | RA.U.MA.VI. BAMOTAR ME KASHA KASH NIRMAN KARYA Other — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹500,000 against a ₹184,000 median for Other works in PRATAPGARH (172% above, 252 peer works)
- 706 days beyond expected completion
| PRATAPGARH | ₹5.00 L | MEDIUM 52 | |
| 15 | RA.U.MA.VI BARI ME KASHA KASH NIRMA KARYA Education — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹500,000 against a ₹80,400 median for Education works in PRATAPGARH (522% above, 216 peer works)
- 706 days beyond expected completion
| PRATAPGARH | ₹5.00 L | MEDIUM 52 | |
| 16 | RA.U.MA.VI AMBEERAMA ME KASHA KASH NIRMA KARAY Education — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹500,000 against a ₹80,400 median for Education works in PRATAPGARH (522% above, 216 peer works)
- 706 days beyond expected completion
| PRATAPGARH | ₹5.00 L | MEDIUM 52 | |
| 17 | near vaga bavji devsathan, barhadri chotra nirmaan Religious & Cultural — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹500,000 against a ₹200,000 median for Religious & Cultural works in PRATAPGARH (150% above, 49 peer works)
- 205 days beyond expected completion
| PRATAPGARH | ₹5.00 L | MEDIUM 52 | |
| 18 | community hall, gadariyawas Community Buildings — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in PRATAPGARH (100% above, 96 peer works)
- 205 days beyond expected completion
| PRATAPGARH | ₹10.00 L | MEDIUM 52 | |
| 19 | dom development in GSSS chiklad Community Buildings — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in PRATAPGARH (100% above, 96 peer works)
- 277 days beyond expected completion
| PRATAPGARH | ₹10.00 L | MEDIUM 52 | |
| 20 | Construction of CC Road near the temple from CC Road in Baba Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,226,037 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (181% above, 370 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹12.26 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 21 | Legislative Assembly- Rampur Khas, Tehsil- Lalganj, District Street Lighting — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹962,576 against a ₹185,858 median for Street Lighting works in PRATAPGARH (418% above, 586 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 26 payments still in progress, oldest 377 days
| PRATAPGARH | ₹9.63 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 22 | Construction of CC Road near the temple from CC Road in Baba Roads & Paving — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹1,226,037 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (181% above, 370 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹12.26 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 23 | Legislative Assembly- Rampur Khas, Tehsil- Lalganj, District Street Lighting — PRATAPGARH(DISTRICT MAGISTRAE PRATAPGARH_IDA) - ₹962,576 against a ₹185,858 median for Street Lighting works in PRATAPGARH (418% above, 586 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 176 payments still in progress, oldest 377 days
| PRATAPGARH | ₹9.63 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 24 | bridge construction work
(Construction work of Bhiyahuri pul Roads & Paving — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - Completed work has no photographic documentation on record
- ₹1,394,484 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (219% above, 370 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| PRATAPGARH | ₹13.94 L | MEDIUM 51
cost 25duplication 20compliance 5 | |
| 25 | bridge construction work
(Construction work of Bhiyahuri pul Roads & Paving — PRATAPGARH(DISTRICT COLLECTOR PRATAPGARH_IDA) - Completed work has no photographic documentation on record
- ₹1,394,484 against a ₹436,870 median for Roads & Paving works in PRATAPGARH (219% above, 370 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| PRATAPGARH | ₹13.94 L | MEDIUM 51
cost 25duplication 20compliance 5 | |