| 1 | GRAM NAI MEIN EK YUVA BHAUDESHYA BHAWAN EVAM TOILET KA NIRMA Drainage & Sanitation — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - ₹500,000 against a ₹200,000 median for Drainage & Sanitation works in NAINITAL (150% above, 30 peer works)
- 329 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | Electrification in Scheduled Caste dominated village Rampur, Street Lighting — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - ₹1,200,000 against a ₹220,000 median for Street Lighting works in NAINITAL (445% above, 29 peer works)
- 381 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | GRAM NAI MEIN EK YUVA BHAUDESHYA BHAWAN EVAM TOILET KA NIRMA Drainage & Sanitation — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - ₹500,000 against a ₹200,000 median for Drainage & Sanitation works in NAINITAL (150% above, 30 peer works)
- 329 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹5.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | Electrification in Scheduled Caste dominated village Rampur, Street Lighting — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - ₹1,200,000 against a ₹220,000 median for Street Lighting works in NAINITAL (445% above, 29 peer works)
- 381 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Construction of basketball court at Bhartiya Shaheed Sainik Education — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - ₹1,146,000 against a ₹250,000 median for Education works in NAINITAL (358% above, 101 peer works)
- 169 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹11.46 L | HIGH 76
cost 25delay 23duplication 20 | |
| 6 | Construction of basketball court at Bhartiya Shaheed Sainik Education — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - ₹1,146,000 against a ₹250,000 median for Education works in NAINITAL (358% above, 101 peer works)
- 169 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹11.46 L | HIGH 76
cost 25delay 23duplication 20 | |
| 7 | Janpad Nainital ke antargat ward number 2 c r s t Inter Coll Education — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - ₹500,000 against a ₹250,000 median for Education works in NAINITAL (100% above, 101 peer works)
- 194 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹5.00 L | MEDIUM 65
cost 25delay 25duplication 8 | |
| 8 | GRAM PATKOT MEIN MEIN LT LINE KO JANHIT MEIN SURAKSHIT STHAN Street Lighting — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 555 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹45,266 | MEDIUM 63
delay 25duplication 20cost 10 | |
| 9 | GRAM PATKOT MEIN MEIN LT LINE KO JANHIT MEIN SURAKSHIT STHAN Street Lighting — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 555 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹45,266 | MEDIUM 63
delay 25duplication 20cost 10 | |
| 10 | Janpad Nainital ke antargat gram sasbani letibunga vikaskhan Drainage & Sanitation — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 618 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.00 L | MEDIUM 60
delay 25duplication 20cost 7 | |
| 11 | Janpad Nainital ke antargat gram sasbani letibunga vikaskhan Drainage & Sanitation — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 618 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.00 L | MEDIUM 60
delay 25duplication 20cost 7 | |
| 12 | Janpad Nainital ke antargat gram Sarna vikaskhand Dhari Mein Community Buildings — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 618 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.00 L | MEDIUM 60
delay 25duplication 20cost 7 | |
| 13 | Janpad Nainital ke antargat gram Alchona Tahsil Nainital vik Roads & Paving — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 603 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.00 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 14 | Janpad Nainital ke antargat gram Alchona Tahsil Nainital vik Roads & Paving — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 603 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.00 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 15 | Janpad Nainital antargat gram bacchi Nagar number 2 Mein lin Roads & Paving — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 214 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.50 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 16 | Janpad Nainital ke antargat mein gram Majuli tahsildari dhar Roads & Paving — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 214 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.50 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 17 | Janpad Nainital ke antargat mein gram Majuli tahsildari dhar Roads & Paving — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 214 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.50 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 18 | janpad Nainital ke antargat Gram Sabha alchoana ke antargat Boundary & Protection — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 215 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.50 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 19 | Janpad Nainital ke Gram Sabha badhit vikaskhand bheemtal Mei Roads & Paving — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 205 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.00 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 20 | Janpad Nainital ke Gram Sabha badhit vikaskhand bheemtal Mei Roads & Paving — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 205 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.00 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 21 | janpad Nainital ke antargat Gram Sabha alchoana ke antargat Boundary & Protection — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 208 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.50 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 22 | Janpad Nainital ke antargat gram sabha alchona Vikas Khand b Boundary & Protection — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 220 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹1.00 L | MEDIUM 59
delay 25duplication 18cost 8 | |
| 23 | Janpad Nainital ke antargat gram sabha alchona Vikas Khand b Boundary & Protection — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 220 days beyond expected completion
- 99% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹1.00 L | MEDIUM 59
delay 25duplication 18cost 8 | |
| 24 | Janpad Nainital ke antargat gram Gujroda lamachaur Haldwani Community Buildings — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 194 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.50 L | MEDIUM 59
delay 25duplication 20agency 7 | |
| 25 | Janpad Nainital ke antargat gram Gujroda lamachaur Haldwani Community Buildings — NAINITAL(DISTRICT MAGISTRATE NAINITAL_IDA) - 194 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 48% delay rate across its projects
| NAINITAL | ₹2.50 L | MEDIUM 59
delay 25duplication 20agency 7 | |