| 1 | Thakurani community centre Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - 580 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹2.00 L | MEDIUM 59
delay 25duplication 20cost 7 | |
| 2 | CC Road at Bhandariguda GP-Bhandariguda Roads & Paving — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in NABARANGPUR (150% above, 74 peer works)
- 559 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 57 | |
| 3 | improvement of Sista Karana Community centre Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 580 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 57 | |
| 4 | Construction of CC Road at Chitrokote Church Road Roads & Paving — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in NABARANGPUR (150% above, 74 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 5 | Repair of Christian Community Centre at Chitrokote Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (300% above, 209 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹10.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 6 | Near Maa Dhanda Dharani Community Centre at Bamuni Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 7 | Construction of CC Road at Chitrokote Church Road Roads & Paving — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in NABARANGPUR (150% above, 74 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 8 | Repair of Christian Community Centre at Chitrokote Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (300% above, 209 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹10.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 9 | Near Maa Dhanda Dharani Community Centre at Bamuni Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |
| 10 | Construction of additional class rooms at Saraswati Sishu Vi Religious & Cultural — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹1,000,000 against a ₹499,826 median for Religious & Cultural works in NABARANGPUR (100% above, 16 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹10.00 L | MEDIUM 47 | |
| 11 | Construction of additional class room at Saraswati Sishu Vid Religious & Cultural — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹1,000,000 against a ₹499,826 median for Religious & Cultural works in NABARANGPUR (100% above, 16 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹10.00 L | MEDIUM 47 | |
| 12 | Construction of additional class room at Saraswati Sishu Vid Religious & Cultural — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹1,000,000 against a ₹499,826 median for Religious & Cultural works in NABARANGPUR (100% above, 16 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹10.00 L | MEDIUM 47 | |
| 13 | CC Road At Dhepguda (Potapada) GP- Malgam Roads & Paving — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹300,000 against a ₹200,000 median for Roads & Paving works in NABARANGPUR (50% above, 74 peer works)
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹3.00 L | MEDIUM 44 | |
| 14 | Construction of Meditation Hall and Rajyoga Training Centre, Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 15 | Construction of Community Building at Dabugaon Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 16 | Construction of Community Centre near Maa Sunadei at village Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 17 | Construction of Community Centre near Maa Semileani at Junap Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 18 | Construction of Community Centre near Trinath Mandir, Sarugu Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 19 | Completion of partly constructed community Centre at Narsing Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 20 | Construction of Community Centre near Maa Bhandar Gharani Ma Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 21 | Construction of Community Centre near Pendrani Mandir at vil Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 22 | Construction of pucca Community Sitting area with tin roof n Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 23 | Construction of Community Centre at village-Gurusingha Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 24 | Construction of Community Centre near Alekha Mahima Tungi at Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |
| 25 | Construction of Community Centre near Kali Mandir at Anchala Community Buildings — NABARANGPUR(DISTRICT COLLECTOR NABARANGPUR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in NABARANGPUR (100% above, 209 peer works)
- 83 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 45% delay rate across its projects
| NABARANGPUR | ₹5.00 L | MEDIUM 43 | |