| 1 | Construction of Boundary Wall Boundary & Protection — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹20,000 median for Boundary & Protection works in MANDI (1400% above, 106 peer works)
- 226 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 2 | Installation of Open Multi Gym Equipment at Panchayat Chhapr Sports — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹500,000 against a ₹100,000 median for Sports works in MANDI (400% above, 45 peer works)
- 719 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹5.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 3 | C/o Rain Water Drainage Cement Pipe from Ubak Ground to the Roads & Paving — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹150,000 median for Roads & Paving works in MANDI (100% above, 257 peer works)
- 719 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 4 | Purchase of Books for Thirty (30) GSSS, Schools of Distt. Ma Education — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹3,000,000 against a ₹500,000 median for Education works in MANDI (500% above, 20 peer works)
- 747 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹30.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 5 | Construction of Boundary Wall Boundary & Protection — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹20,000 median for Boundary & Protection works in MANDI (1400% above, 106 peer works)
- 226 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 6 | Installation of Open Multi Gym Equipment at Panchayat Chhapr Sports — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹500,000 against a ₹100,000 median for Sports works in MANDI (400% above, 45 peer works)
- 719 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹5.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 7 | C/o Rain Water Drainage Cement Pipe from Ubak Ground to the Roads & Paving — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹150,000 median for Roads & Paving works in MANDI (100% above, 257 peer works)
- 719 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 8 | Purchase of Books for Thirty (30) GSSS, Schools of Distt. Ma Education — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹3,000,000 against a ₹500,000 median for Education works in MANDI (500% above, 20 peer works)
- 747 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹30.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 9 | Construction of room Saraswati Vidya Mandir Religious & Cultural — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹150,000 median for Religious & Cultural works in MANDI (100% above, 33 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 72
cost 25delay 21duplication 20 | |
| 10 | Construction of room Saraswati Vidya Mandir Religious & Cultural — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹150,000 median for Religious & Cultural works in MANDI (100% above, 33 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹3.00 L | HIGH 72
cost 25delay 21duplication 20 | |
| 11 | Solar light in Gp cheli Street Lighting — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹150,000 against a ₹50,000 median for Street Lighting works in MANDI (200% above, 31 peer works)
- 98 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹1.50 L | MEDIUM 64
cost 25duplication 20delay 14 | |
| 12 | Repair of 22 Solar light in Gp cheli Street Lighting — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹110,649 against a ₹50,000 median for Street Lighting works in MANDI (121% above, 31 peer works)
- 98 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹1.11 L | MEDIUM 64
cost 25duplication 20delay 14 | |
| 13 | Solar light in Gp cheli Street Lighting — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹150,000 against a ₹50,000 median for Street Lighting works in MANDI (200% above, 31 peer works)
- 98 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹1.50 L | MEDIUM 64
cost 25duplication 20delay 14 | |
| 14 | Repair of 22 Solar light in Gp cheli Street Lighting — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹110,649 against a ₹50,000 median for Street Lighting works in MANDI (121% above, 31 peer works)
- 98 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MANDI | ₹1.11 L | MEDIUM 64
cost 25duplication 20delay 14 | |
| 15 | C/o Community Centre/Hall for reading/Library in Village, G. Education — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - 656 days beyond expected completion
- 100% similarity with another nearby work
| MANDI | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 9 | |
| 16 | C/o Community Centre/Hall for reading/Library in Village, G. Education — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - 656 days beyond expected completion
- 100% similarity with another nearby work
| MANDI | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 9 | |
| 17 | C/o Under Construction Bridge Doghari Nichla Naal near Ghara Roads & Paving — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - 288 days beyond expected completion
- 100% similarity with another nearby work
| MANDI | ₹1.50 L | MEDIUM 58
delay 25duplication 20cost 8 | |
| 18 | C/o Under Construction Bridge Doghari Nichla Naal near Ghara Roads & Paving — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - 288 days beyond expected completion
- 100% similarity with another nearby work
| MANDI | ₹1.50 L | MEDIUM 58
delay 25duplication 20cost 8 | |
| 19 | C/o Community Bhawan at Village Kashaud G.P. Kashaud Dev. Bl Community Buildings — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - 288 days beyond expected completion
- 100% similarity with another nearby work
| MANDI | ₹2.50 L | MEDIUM 58
delay 25duplication 20cost 8 | |
| 20 | C/o Community Bhawan at Village Kashaud G.P. Kashaud Dev. Bl Community Buildings — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - 288 days beyond expected completion
- 100% similarity with another nearby work
| MANDI | ₹2.50 L | MEDIUM 58
delay 25duplication 20cost 8 | |
| 21 | Purchase of books for public library for different Governmen Education — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in MANDI (400% above, 20 peer works)
- 100% similarity with another nearby work
| MANDI | ₹25.00 L | MEDIUM 57
cost 25duplication 20delay 7 | |
| 22 | Purchase of books for public library for different Governmen Education — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in MANDI (400% above, 20 peer works)
- 100% similarity with another nearby work
| MANDI | ₹25.00 L | MEDIUM 57
cost 25duplication 20delay 7 | |
| 23 | Construction of Path alongwith protection wall near the hous Boundary & Protection — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 572 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| MANDI | ₹20,000 | MEDIUM 56
delay 25duplication 16cost 10 | |
| 24 | Construction of Path alongwith protection wall near the hous Boundary & Protection — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 572 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| MANDI | ₹20,000 | MEDIUM 56
delay 25duplication 16cost 10 | |
| 25 | c/o road from Kufri Dhar to Khanyari in Gram Panchayat Seri Roads & Paving — MANDI(DEPUTY COMMISSIONER MANDI_IDA) - ₹300,000 against a ₹150,000 median for Roads & Paving works in MANDI (100% above, 257 peer works)
- 544 days beyond expected completion
| MANDI | ₹3.00 L | MEDIUM 55 | |