| 1 | Kolhapur Municipal Corporation Ward No. 40 Construction of i Roads & Paving — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹2,500,000 against a ₹999,000 median for Roads & Paving works in KOLHAPUR (150% above, 205 peer works)
- 336 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹25.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 2 | Kolhapur Municipal Corporation Ward No. 40 Construction of i Roads & Paving — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹2,500,000 against a ₹999,000 median for Roads & Paving works in KOLHAPUR (150% above, 205 peer works)
- 336 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹25.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 3 | Gram Jattewadi, Ta. Chandgad, Dist. Kolhapur me Cultural Hal Community Buildings — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in KOLHAPUR (50% above, 85 peer works)
- 345 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 4 | Gram Jattewadi, Ta. Chandgad, Dist. Kolhapur me Cultural Hal Community Buildings — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in KOLHAPUR (50% above, 85 peer works)
- 345 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 5 | Kolhapur Municipal Corporation Ward No. 17 Construction of r Roads & Paving — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹1,500,000 against a ₹999,000 median for Roads & Paving works in KOLHAPUR (50% above, 205 peer works)
- 336 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 6 | Kolhapur Municipal Corporation Ward No. 17 Construction of r Roads & Paving — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹1,500,000 against a ₹999,000 median for Roads & Paving works in KOLHAPUR (50% above, 205 peer works)
- 336 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹15.00 L | MEDIUM 61
delay 25duplication 20cost 14 | |
| 7 | Walking track / compound Boundary & Protection — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 343 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 59
delay 25duplication 20cost 12 | |
| 8 | Walking track / compound Boundary & Protection — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 343 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 59
delay 25duplication 20cost 12 | |
| 9 | Compound Wall / Fencing Boundary & Protection — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 10 | Compound Wall / Fencing Boundary & Protection — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 11 | Hall / Compound Wall Community Buildings — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 12 | Recreation Center / Hall Community Buildings — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 13 | Compound Wall / Fencing Boundary & Protection — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 14 | Compound Wall / Fencing Boundary & Protection — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 15 | Hall / Compound Wall Community Buildings — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 16 | Recreation Center / Hall Community Buildings — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 331 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 58
delay 25duplication 20cost 12 | |
| 17 | Concreting of the passage road from Lingam Home to Shirale H Roads & Paving — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹2,000,000 against a ₹999,000 median for Roads & Paving works in KOLHAPUR (100% above, 205 peer works)
- 100% similarity with another nearby work
| KOLHAPUR | ₹20.00 L | MEDIUM 57
cost 25duplication 20delay 10 | |
| 18 | Concreting of the passage road from Lingam Home to Shirale H Roads & Paving — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹2,000,000 against a ₹999,000 median for Roads & Paving works in KOLHAPUR (100% above, 205 peer works)
- 100% similarity with another nearby work
| KOLHAPUR | ₹20.00 L | MEDIUM 57
cost 25duplication 20delay 10 | |
| 19 | Cultural hall Community Buildings — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - 226 days beyond expected completion
- 100% similarity with another nearby work
| KOLHAPUR | ₹10.00 L | MEDIUM 57
delay 25duplication 20cost 10 | |
| 20 | Purchase of Computer & Printer for Primary School Vhannur, T Education — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - 357 days beyond expected completion
- 100% similarity with another nearby work
| KOLHAPUR | ₹1.50 L | MEDIUM 55
delay 25duplication 20cost 9 | |
| 21 | Purchase of Computer & Printer for Primary School Vhannur, T Education — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - 357 days beyond expected completion
- 100% similarity with another nearby work
| KOLHAPUR | ₹1.50 L | MEDIUM 55
delay 25duplication 20cost 9 | |
| 22 | Providing Water Purifier (2), Computer (3) to Hutatma Babu G Water — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹204,000 against a ₹103,160 median for Water works in KOLHAPUR (98% above, 51 peer works)
- 100% similarity with another nearby work
| KOLHAPUR | ₹2.04 L | MEDIUM 54
cost 24duplication 20delay 8 | |
| 23 | Providing Water Purifier (2), Computer (3) to Hutatma Babu G Water — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹204,000 against a ₹103,160 median for Water works in KOLHAPUR (98% above, 51 peer works)
- 100% similarity with another nearby work
| KOLHAPUR | ₹2.04 L | MEDIUM 54
cost 24duplication 20delay 8 | |
| 24 | Moje Gargoti Construction of Youth Library at Bhudargarh Education — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹2,499,000 against a ₹175,000 median for Education works in KOLHAPUR (1328% above, 48 peer works)
- 654 days beyond expected completion
| KOLHAPUR | ₹24.99 L | MEDIUM 52 | |
| 25 | Mhasve Construction of Gymnasium at Bhudargarh Gram Panchaya Sports — KOLHAPUR(DISTRICT COLLECTOR KOLHAPUR_IDA) - ₹2,500,000 against a ₹1,000,000 median for Sports works in KOLHAPUR (150% above, 17 peer works)
- 733 days beyond expected completion
| KOLHAPUR | ₹25.00 L | MEDIUM 52 | |