| 1 | nalkup khanan at various wards khandwa Water — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹300,000 against a ₹190,546 median for Water works in KHANDWA (57% above, 27 peer works)
- 338 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹3.00 L | HIGH 71
delay 25duplication 20cost 14 | |
| 2 | nalkup khanan at various wards khandwa Water — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - 338 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹1.50 L | MEDIUM 66
delay 25duplication 20agency 12 | |
| 3 | nalkup khanan at various wards khandwa Water — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - 338 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹1.50 L | MEDIUM 66
delay 25duplication 20agency 12 | |
| 4 | gram panchayat - borgaon buzurg janpad panchayat - pandhana Education — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹500,000 against a ₹100,000 median for Education works in KHANDWA (400% above, 23 peer works)
- 578 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹5.00 L | MEDIUM 65 | |
| 5 | Rameshwar ward no. 47 mai Construction of buildings for comm Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in KHANDWA (100% above, 35 peer works)
- 578 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹5.00 L | MEDIUM 65 | |
| 6 | chabutra shed nirman Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - 247 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹2.00 L | MEDIUM 65
delay 25duplication 20agency 12 | |
| 7 | chabutra shed nirman Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - 247 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹2.50 L | MEDIUM 64
delay 25duplication 20agency 12 | |
| 8 | gram singhaji ke kunbhi patel mohalla mai chabutara tin shed Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in KHANDWA (300% above, 35 peer works)
- 181 days beyond expected completion
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹10.00 L | MEDIUM 62 | |
| 9 | Jhila adhivakta sangh for female members tin shed Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in KHANDWA (300% above, 35 peer works)
- 243 days beyond expected completion
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹10.00 L | MEDIUM 62 | |
| 10 | near kunbhi samaj go shala singot bhavan nirman Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹1,500,000 against a ₹250,000 median for Community Buildings works in KHANDWA (500% above, 35 peer works)
- 336 days beyond expected completion
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹15.00 L | MEDIUM 62 | |
| 11 | sanskrutik bhavan at richfal Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in KHANDWA (100% above, 35 peer works)
- 336 days beyond expected completion
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹5.00 L | MEDIUM 62 | |
| 12 | WARD NUM 35 TIN SHED NEAR MAHALAKSHMI MANDIR Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in KHANDWA (100% above, 35 peer works)
- 338 days beyond expected completion
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹5.00 L | MEDIUM 62 | |
| 13 | chabutra shed near dattatray mandir Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - ₹500,000 against a ₹250,000 median for Community Buildings works in KHANDWA (100% above, 35 peer works)
- 338 days beyond expected completion
Read more (1 more)Show less- 70% of this agency's ₹46,276,293 spend went to one vendor (KPL EQUIPMENTS PRIVATE LIMITED), across 66 vendors and 278 transactions
| KHANDWA | ₹5.00 L | MEDIUM 62 | |
| 14 | Construction of platform shed for public use Ward No. 47 Ram Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹50,000 | MEDIUM 62 | |
| 15 | Construction of platform shed for public use Ward No. 47 Ram Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹50,000 | MEDIUM 62 | |
| 16 | Extension work of motor pump pipe line for drinking water in Water — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹50,000 | MEDIUM 54 | |
| 17 | Construction work of platform with shed for public use near Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹50,000 | MEDIUM 54 | |
| 18 | Construction work of platform with shed for public use near Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹50,000 | MEDIUM 54 | |
| 19 | Motor pump pipe line extension work for drinking water in Dh Water — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹1.00 L | MEDIUM 53 | |
| 20 | Construction of platform shed for public use in village Bhui Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹90,000 | MEDIUM 53 | |
| 21 | Construction of platform shed for public use near Abhimanyu Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹92,000 | MEDIUM 53 | |
| 22 | Pipeline extension work for drinking water in village Barud Water — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 773 days beyond expected completion
Read more (1 more)Show less- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹2.00 L | MEDIUM 53 | |
| 23 | gram panchyat - bhagwanpura janpad panchayat khandwa mai sar Religious & Cultural — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - 578 days beyond expected completion
- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹5.00 L | MEDIUM 48 | |
| 24 | nagar nigam khandwa ke ward no 48 mai love kush nagar garden Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - 578 days beyond expected completion
- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹2.50 L | MEDIUM 48 | |
| 25 | nagar nigam khandwa ke ward no 48 mai deendayal puram mai Co Community Buildings — Khandwa (East Nimar)(DISTRICT COLLECTOR EAST NIMAR_IDA) - 578 days beyond expected completion
- 90% of this agency's ₹30,703,923 spend went to one vendor (KPL Equipments Pvt Ltd bhopal mp), across 20 vendors and 114 transactions
| KHANDWA | ₹2.50 L | MEDIUM 48 | |