| 1 | construction of rooms , kitchen and bathroom etc in sports g Sports — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹3,000,000 against a ₹300,000 median for Sports works in KAPURTHALA (900% above, 28 peer works)
- 391 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹30.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 2 | Construction of Rooms in Gov.Sen.Sec.School, Lakhan Kallan. Education — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,100,000 against a ₹300,000 median for Education works in KAPURTHALA (267% above, 11 peer works)
- 397 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹11.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 3 | For laying sewerage and drainage of dirty water in the villa Water — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,200,000 against a ₹365,800 median for Water works in KAPURTHALA (228% above, 193 peer works)
- 546 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹12.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 4 | Construction of Building of hospital, (Vill. Gram Panchyat B Health — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹990,000 against a ₹482,499 median for Health works in KAPURTHALA (105% above, 12 peer works)
- 736 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹9.90 L | HIGH 75
cost 25delay 25duplication 20 | |
| 5 | Construction of Dharamshala Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹200,000 median for Religious & Cultural works in KAPURTHALA (150% above, 17 peer works)
- 659 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 6 | Construction of Dharamshala Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹200,000 median for Religious & Cultural works in KAPURTHALA (150% above, 17 peer works)
- 659 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 7 | Construction of Dharamshala Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹600,000 against a ₹200,000 median for Religious & Cultural works in KAPURTHALA (200% above, 17 peer works)
- 659 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹6.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 8 | Construction of Dharamshala Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹200,000 median for Religious & Cultural works in KAPURTHALA (150% above, 17 peer works)
- 804 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 9 | construction of rooms , kitchen and bathroom etc in sports g Sports — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹3,000,000 against a ₹300,000 median for Sports works in KAPURTHALA (900% above, 28 peer works)
- 391 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹30.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 10 | Construction of Rooms in Gov.Sen.Sec.School, Lakhan Kallan. Education — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,100,000 against a ₹300,000 median for Education works in KAPURTHALA (267% above, 11 peer works)
- 397 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹11.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 11 | For laying sewerage and drainage of dirty water in the villa Water — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,200,000 against a ₹365,800 median for Water works in KAPURTHALA (228% above, 193 peer works)
- 546 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹12.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 12 | Construction of Building of hospital, (Vill. Gram Panchyat B Health — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹990,000 against a ₹482,499 median for Health works in KAPURTHALA (105% above, 12 peer works)
- 736 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹9.90 L | HIGH 75
cost 25delay 25duplication 20 | |
| 13 | Providing and Laying of interlocking tiles (PWD B&R) Xen KPT Roads & Paving — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹997,000 against a ₹500,000 median for Roads & Paving works in KAPURTHALA (99% above, 44 peer works)
- 736 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹9.97 L | HIGH 75
delay 25cost 25duplication 20 | |
| 14 | Providing and Laying of interlocking tiles (PWD B&R) Xen KPT Roads & Paving — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹997,000 against a ₹500,000 median for Roads & Paving works in KAPURTHALA (99% above, 44 peer works)
- 736 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹9.97 L | HIGH 75
delay 25cost 25duplication 20 | |
| 15 | Construction of Dharamshala Religious & Cultural — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹350,000 against a ₹200,000 median for Religious & Cultural works in KAPURTHALA (75% above, 17 peer works)
- 659 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹3.50 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 16 | Completion of Road Construction from Skoda Showroom NH ONE t Roads & Paving — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in KAPURTHALA (100% above, 44 peer works)
- 126 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹10.00 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 17 | Completion of Road Construction from Skoda Showroom NH ONE t Roads & Paving — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in KAPURTHALA (100% above, 44 peer works)
- 126 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹10.00 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 18 | Construction for Hall in School. Education — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹300,000 median for Education works in KAPURTHALA (67% above, 11 peer works)
- 725 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | MEDIUM 67
delay 25duplication 20cost 17 | |
| 19 | Construction of fixed gym Sports — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹300,000 median for Sports works in KAPURTHALA (67% above, 28 peer works)
- 659 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | MEDIUM 67
delay 25duplication 20cost 17 | |
| 20 | Construction of fixed gym Sports — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹300,000 median for Sports works in KAPURTHALA (67% above, 28 peer works)
- 659 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | MEDIUM 67
delay 25duplication 20cost 17 | |
| 21 | Construction for Hall in School. Education — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹500,000 against a ₹300,000 median for Education works in KAPURTHALA (67% above, 11 peer works)
- 725 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹5.00 L | MEDIUM 67
delay 25duplication 20cost 17 | |
| 22 | Mortuary freezer two box Equipment & Vehicles — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹900,000 against a ₹541,695 median for Equipment & Vehicles works in KAPURTHALA (66% above, 16 peer works)
- 764 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹9.00 L | MEDIUM 67
delay 25duplication 20cost 17 | |
| 23 | Mortuary freezer two box Equipment & Vehicles — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹900,000 against a ₹541,695 median for Equipment & Vehicles works in KAPURTHALA (66% above, 16 peer works)
- 764 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹9.00 L | MEDIUM 67
delay 25duplication 20cost 17 | |
| 24 | Regarding new construction of Ayurvedic Dispensary Sultanpur Health — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹715,000 against a ₹482,499 median for Health works in KAPURTHALA (48% above, 12 peer works)
- 740 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹7.15 L | MEDIUM 64
delay 25duplication 20cost 14 | |
| 25 | Regarding new construction of Ayurvedic Dispensary Sultanpur Health — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹715,000 against a ₹482,499 median for Health works in KAPURTHALA (48% above, 12 peer works)
- 740 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹7.15 L | MEDIUM 64
delay 25duplication 20cost 14 | |