| 1 | For the construction of a hall on the first floor of the com Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (270% above, 55 peer works)
- 225 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹20.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 2 | For the construction of a hall on the first floor of the com Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (270% above, 55 peer works)
- 225 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹20.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 3 | Construction of Grewal Road from Damar Road to Kaudada Mandi Roads & Paving — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,500,000 against a ₹924,624 median for Roads & Paving works in JODHPUR (62% above, 29 peer works)
- 754 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹15.00 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 4 | Construction of Grewal Road from Damar Road to Kaudada Mandi Roads & Paving — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,500,000 against a ₹924,624 median for Roads & Paving works in JODHPUR (62% above, 29 peer works)
- 754 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹15.00 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 5 | To get the work of synthetic basketball court and open gym d Sports — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 225 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹25.00 L | MEDIUM 64
delay 25duplication 20cost 15 | |
| 6 | To get the work of synthetic basketball court and open gym d Sports — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 225 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹25.00 L | MEDIUM 64
delay 25duplication 20cost 15 | |
| 7 | Construction of public toilet at drinker (Pyau) at Gajsingh Drainage & Sanitation — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 754 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹7.00 L | MEDIUM 63
delay 25duplication 20cost 14 | |
| 8 | Construction of public toilet at drinker (Pyau) at Gajsingh Drainage & Sanitation — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 754 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹7.00 L | MEDIUM 63
delay 25duplication 20cost 14 | |
| 9 | sampark sadak se gaayadasinh kee dhaaniyon tak greval sadak Roads & Paving — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹10.00 L | MEDIUM 61
delay 25duplication 20cost 12 | |
| 10 | sampark sadak se gaayadasinh kee dhaaniyon tak greval sadak Roads & Paving — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 604 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹10.00 L | MEDIUM 61
delay 25duplication 20cost 12 | |
| 11 | MPLADS - 162
Construction work of a hall in Khasra No. 62/1 Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,600,000 against a ₹541,167 median for Community Buildings works in JODHPUR (196% above, 55 peer works)
- 605 days beyond expected completion
| JODHPUR | ₹16.00 L | MEDIUM 54 | |
| 12 | TIN SHED NIRMAN KARYA, NEAR DEVRI DHAM, GRAMPANCHAYAT KI ADH Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,100,000 against a ₹541,167 median for Community Buildings works in JODHPUR (288% above, 55 peer works)
- 770 days beyond expected completion
| JODHPUR | ₹21.00 L | MEDIUM 54 | |
| 13 | TIN SHED NIRMAN KARYA, NEAR VEER TEJAJI MANDIR ,DANGIYAWAS,M Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,100,000 against a ₹541,167 median for Community Buildings works in JODHPUR (288% above, 55 peer works)
- 771 days beyond expected completion
| JODHPUR | ₹21.00 L | MEDIUM 54 | |
| 14 | MPLADS - 86
Development work including construction of hall Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (85% above, 55 peer works)
- 734 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 50 | |
| 15 | TIN SHED NIRMAN KARYA, KHEL MEDAN ME, PAVELIYAN KHANGTA,PIPA Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (85% above, 55 peer works)
- 742 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 50 | |
| 16 | SAMUDAYIK SHABHA BHAWAN VISHNOI SAMAJ SARVJANIK BHUMI, PIPAD Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (85% above, 55 peer works)
- 770 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 50 | |
| 17 | TIN SHED NIRMAN KARYA,RAJPUT SAMAJ SUDHAR SIKSHA SMITI,BAWDI Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹1,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (85% above, 55 peer works)
- 771 days beyond expected completion
| JODHPUR | ₹10.00 L | MEDIUM 50 | |
| 18 | Construction of Public Libraries and Reading Rooms at Gram P Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Completed work has no photographic documentation on record
- ₹999,858 against a ₹541,167 median for Community Buildings works in JODHPUR (85% above, 55 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹10.00 L | MEDIUM 50
cost 21duplication 20compliance 5 | |
| 19 | Construction of Public Libraries and Reading Rooms at Gram P Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Completed work has no photographic documentation on record
- ₹999,858 against a ₹541,167 median for Community Buildings works in JODHPUR (85% above, 55 peer works)
Read more (1 more)Show less- 100% similarity with another nearby work
| JODHPUR | ₹10.00 L | MEDIUM 50
cost 21duplication 20compliance 5 | |
| 20 | TIN SHED NIRMAN KARYA ,RAJKIYA UCCH PRATMIK VIDYALAY ,GODAWA Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 742 days beyond expected completion
Read more (1 more)Show less- 97% similarity with another nearby work
| JODHPUR | ₹5.00 L | MEDIUM 49
delay 25cost 11duplication 9 | |
| 21 | Other construction related works including a permanent ghat Water — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,000,000 against a ₹750,000 median for Water works in JODHPUR (167% above, 11 peer works)
- 100% similarity with another nearby work
| JODHPUR | ₹20.00 L | MEDIUM 49
cost 25duplication 20agency 4 | |
| 22 | Work for the laying of pipelines to improve water supply in Water — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,000,000 against a ₹750,000 median for Water works in JODHPUR (167% above, 11 peer works)
- 100% similarity with another nearby work
| JODHPUR | ₹20.00 L | MEDIUM 49
cost 25duplication 20agency 4 | |
| 23 | Construction of RCC Chambers G plus 1 at Rajasthan High Cour Community Buildings — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹10,000,000 against a ₹541,167 median for Community Buildings works in JODHPUR (1748% above, 55 peer works)
- 100% similarity with another nearby work
| JODHPUR | ₹1.00 Cr | MEDIUM 49
cost 25duplication 20agency 4 | |
| 24 | Other construction related works including a permanent ghat Water — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,000,000 against a ₹750,000 median for Water works in JODHPUR (167% above, 11 peer works)
- 100% similarity with another nearby work
| JODHPUR | ₹20.00 L | MEDIUM 49
cost 25duplication 20agency 4 | |
| 25 | Work for the laying of pipelines to improve water supply in Water — JODHPUR(DISTRICT COLLECTOR JODHPUR IDA) - ₹2,000,000 against a ₹750,000 median for Water works in JODHPUR (167% above, 11 peer works)
- 100% similarity with another nearby work
| JODHPUR | ₹20.00 L | MEDIUM 49
cost 25duplication 20agency 4 | |