| 1 | Construction of RO System (500-100 Lph) Including Water Cool Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,100,000 against a ₹175,000 median for Water works in JIND (529% above, 156 peer works)
- 210 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹11.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Construction of RO System (500-100 Lph) Including Water Cool Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,100,000 against a ₹175,000 median for Water works in JIND (529% above, 156 peer works)
- 210 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹11.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Const. of General Chaupal Community Buildings — JIND(DEPUTY COMMISSIONER JIND) - ₹999,648 against a ₹500,000 median for Community Buildings works in JIND (100% above, 87 peer works)
- 139 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹10.00 L | MEDIUM 70
cost 25duplication 20delay 19 | |
| 4 | Construction of Cycle Stand, Painting of School, and Ro Wate Water — JIND(DEPUTY COMMISSIONER JIND) - ₹497,024 against a ₹175,000 median for Water works in JIND (184% above, 156 peer works)
- 119 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹4.97 L | MEDIUM 67
cost 25duplication 20delay 17 | |
| 5 | Construction of Cycle Stand, Painting of School, and Ro Wate Water — JIND(DEPUTY COMMISSIONER JIND) - ₹497,024 against a ₹175,000 median for Water works in JIND (184% above, 156 peer works)
- 119 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹4.97 L | MEDIUM 67
cost 25duplication 20delay 17 | |
| 6 | Const. of kabir chaupal Community Buildings — JIND(DEPUTY COMMISSIONER JIND) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 727 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JIND | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 11 | |
| 7 | Provide one water tanker Water — JIND(DEPUTY COMMISSIONER JIND) - 695 days beyond expected completion
- 100% similarity with another nearby work
| JIND | ₹1.57 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 8 | Provide one water tanker Water — JIND(DEPUTY COMMISSIONER JIND) - 695 days beyond expected completion
- 100% similarity with another nearby work
| JIND | ₹1.57 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 9 | Provide one water tanker Water — JIND(DEPUTY COMMISSIONER JIND) - 643 days beyond expected completion
- 100% similarity with another nearby work
| JIND | ₹1.57 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 10 | Renovation Compilation of Library Sarv Jatiya Panchayat Bina Education — JIND(DEPUTY COMMISSIONER JIND) - ₹2,097,682 against a ₹392,564 median for Education works in JIND (434% above, 43 peer works)
- 100% similarity with another nearby work
| JIND | ₹20.98 L | MEDIUM 56
cost 25duplication 20delay 6 | |
| 11 | Renovation Compilation of Library Sarv Jatiya Panchayat Bina Education — JIND(DEPUTY COMMISSIONER JIND) - ₹2,097,682 against a ₹392,564 median for Education works in JIND (434% above, 43 peer works)
- 100% similarity with another nearby work
| JIND | ₹20.98 L | MEDIUM 56
cost 25duplication 20delay 6 | |
| 12 | Const. of shed & floor near water supply no. 3 Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,000,000 against a ₹175,000 median for Water works in JIND (471% above, 156 peer works)
- 687 days beyond expected completion
| JIND | ₹10.00 L | MEDIUM 56 | |
| 13 | Construction of Moga no 13820 on Barwala Minor in village Do Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,000,000 against a ₹175,000 median for Water works in JIND (471% above, 156 peer works)
- 700 days beyond expected completion
| JIND | ₹10.00 L | MEDIUM 56 | |
| 14 | Const. of Ravidas Chaupal Community Buildings — JIND(DEPUTY COMMISSIONER JIND) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JIND (100% above, 87 peer works)
- 727 days beyond expected completion
| JIND | ₹10.00 L | MEDIUM 56 | |
| 15 | Development works for Advocate District Courts Jind Community Buildings — JIND(DEPUTY COMMISSIONER JIND) - ₹1,100,000 against a ₹500,000 median for Community Buildings works in JIND (120% above, 87 peer works)
- 741 days beyond expected completion
| JIND | ₹11.00 L | MEDIUM 56 | |
| 16 | Construction of Kanadi Shed in Jai Baba Jeetgar Kabadi Yuva Community Buildings — JIND(DEPUTY COMMISSIONER JIND) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JIND (100% above, 87 peer works)
- 741 days beyond expected completion
| JIND | ₹10.00 L | MEDIUM 56 | |
| 17 | Development work in Pt. Ghasi Ram Kanya Gurukul College for Education — JIND(DEPUTY COMMISSIONER JIND) - ₹1,000,000 against a ₹392,564 median for Education works in JIND (155% above, 43 peer works)
- 180 days beyond expected completion
| JIND | ₹10.00 L | MEDIUM 56 | |
| 18 | Beautification of Pindara tirath sathal Religious & Cultural — JIND(DEPUTY COMMISSIONER JIND) - ₹1,990,000 against a ₹500,000 median for Religious & Cultural works in JIND (298% above, 9 peer works)
- 180 days beyond expected completion
| JIND | ₹19.90 L | MEDIUM 56 | |
| 19 | Development work of Nirakar Jyoti Education Society Education — JIND(DEPUTY COMMISSIONER JIND) - ₹1,900,000 against a ₹392,564 median for Education works in JIND (384% above, 43 peer works)
- 180 days beyond expected completion
| JIND | ₹19.00 L | MEDIUM 56 | |
| 20 | Const. of B-wall both side (5 foot) on the path between the Roads & Paving — JIND(DEPUTY COMMISSIONER JIND) - ₹1,193,484 against a ₹521,426 median for Roads & Paving works in JIND (129% above, 40 peer works)
- 180 days beyond expected completion
| JIND | ₹11.93 L | MEDIUM 56 | |
| 21 | Construction of E-Library in Ch. Chhotu Ram Memorial Trust N Education — JIND(DEPUTY COMMISSIONER JIND) - ₹1,099,769 against a ₹392,564 median for Education works in JIND (180% above, 43 peer works)
- 171 days beyond expected completion
| JIND | ₹11.00 L | MEDIUM 54 | |
| 22 | in GMS school 5659 Education — JIND(DEPUTY COMMISSIONER JIND) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 740 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| JIND | ₹2.98 L | MEDIUM 54
delay 25duplication 13cost 11 | |
| 23 | in GMS school 5656 Education — JIND(DEPUTY COMMISSIONER JIND) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 740 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| JIND | ₹2.98 L | MEDIUM 54
delay 25duplication 13cost 11 | |
| 24 | construction of water canal To the left of Moga No 26650, Ba Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,000,000 against a ₹175,000 median for Water works in JIND (471% above, 156 peer works)
- 100% similarity with another nearby work
| JIND | ₹10.00 L | MEDIUM 51
cost 25duplication 20agency 6 | |
| 25 | construction of water canal To the left of Moga No 26650, Ba Water — JIND(DEPUTY COMMISSIONER JIND) - ₹1,000,000 against a ₹175,000 median for Water works in JIND (471% above, 156 peer works)
- 100% similarity with another nearby work
| JIND | ₹10.00 L | MEDIUM 51
cost 25duplication 20agency 6 | |