| 1 | Erection of Gandhian Heritage Gate near Government Ayurvedic Health — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Health works in JAJPUR (100% above, 26 peer works)
- 192 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Upgradation of Auditorium Hall in Municipal High School unde Education — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹12,500,000 against a ₹1,000,000 median for Education works in JAJPUR (1150% above, 96 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹1.25 Cr | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Construction of Women’s recreation club of Women’s Capacity Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Construction of Board Room of Women’s Capacity Building Cent Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 5 | Construction of Hobby & Training Center of Women’s Capacity Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 6 | Construction of Office and Admin Room of Women’s Capacity Bu Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 7 | Construction of Reception & Waiting Hall of Zilla Sainik Boa Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 8 | Construction of Office & Accounts Room of Zilla Sainik Board Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 9 | Construction of Record Room of Zilla Sainik Board in Jajpur, Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 10 | Construction of Meeting Room of Zilla Sainik Board in Jajpur Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 11 | Construction of Secretary Cabin of Zilla Sainik Board in Jaj Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 12 | Completion of Boys Toilet of Biraja High School, Ward No.18, Drainage & Sanitation — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in JAJPUR (100% above, 10 peer works)
- 740 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 13 | Completion of Girls Toilet of Biraja High School, Ward No.18 Drainage & Sanitation — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in JAJPUR (100% above, 10 peer works)
- 740 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 14 | Erection of Gandhian Heritage Gate near Government Ayurvedic Health — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Health works in JAJPUR (100% above, 26 peer works)
- 192 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 15 | Upgradation of Auditorium Hall in Municipal High School unde Education — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹12,500,000 against a ₹1,000,000 median for Education works in JAJPUR (1150% above, 96 peer works)
- 589 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹1.25 Cr | HIGH 76
cost 25delay 25duplication 20 | |
| 16 | Construction of Women’s recreation club of Women’s Capacity Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 17 | Construction of Board Room of Women’s Capacity Building Cent Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 18 | Construction of Hobby & Training Center of Women’s Capacity Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 19 | Construction of Office and Admin Room of Women’s Capacity Bu Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 621 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 20 | Construction of Reception & Waiting Hall of Zilla Sainik Boa Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 21 | Construction of Office & Accounts Room of Zilla Sainik Board Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 22 | Construction of Record Room of Zilla Sainik Board in Jajpur, Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 23 | Construction of Meeting Room of Zilla Sainik Board in Jajpur Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 24 | Construction of Secretary Cabin of Zilla Sainik Board in Jaj Community Buildings — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in JAJPUR (100% above, 188 peer works)
- 629 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 25 | Completion of Boys Toilet of Biraja High School, Ward No.18, Drainage & Sanitation — Jajpur(DISTRICT COLLECTOR JAJPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Drainage & Sanitation works in JAJPUR (100% above, 10 peer works)
- 740 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAJPUR | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |