| 1 | Construction of Compound wall to ZPHS School in Chilvakodur Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 303 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 2 | Construction of Community Hall at Korutla Town of Jagtial Di Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹5,000,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (1567% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹50.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 3 | C/o Library Hall at Buggaram (v) in Jagtial Dist Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 4 | C/o Culvert at Muddapally (v) Pegadapally (m) in Jagtial Dis Roads & Paving — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹499,992 median for Roads & Paving works in JAGITIAL (100% above, 117 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 5 | Balance work of Amaraveerula Sthupam and Park, jagitial town Sports — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹495,725 median for Sports works in JAGITIAL (102% above, 16 peer works)
- 561 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 6 | Construction of Compound wall to ZPHS School in Chilvakodur Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 303 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 7 | Construction of Community Hall at Korutla Town of Jagtial Di Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹5,000,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (1567% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹50.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 8 | C/o Library Hall at Buggaram (v) in Jagtial Dist Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 9 | C/o Culvert at Muddapally (v) Pegadapally (m) in Jagtial Dis Roads & Paving — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹499,992 median for Roads & Paving works in JAGITIAL (100% above, 117 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 10 | Balance work of Amaraveerula Sthupam and Park, jagitial town Sports — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹495,725 median for Sports works in JAGITIAL (102% above, 16 peer works)
- 561 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 11 | Provide Additional Structure to Community Hall at Ward No.1, Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹3,000,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (900% above, 276 peer works)
- 150 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹30.00 L | MEDIUM 70
cost 25delay 21duplication 20 | |
| 12 | Provide Additional Structure to Community Hall at Ward No.1, Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹3,000,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (900% above, 276 peer works)
- 150 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹30.00 L | MEDIUM 70
cost 25delay 21duplication 20 | |
| 13 | Balance works of Store Rooms, Annadaana Mandapam Near Navadu Religious & Cultural — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹5,000,000 against a ₹497,500 median for Religious & Cultural works in JAGITIAL (905% above, 22 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹50.00 L | MEDIUM 67
cost 25duplication 20delay 18 | |
| 14 | Balance works of Store Rooms, Annadaana Mandapam Near Navadu Religious & Cultural — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹5,000,000 against a ₹497,500 median for Religious & Cultural works in JAGITIAL (905% above, 22 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹50.00 L | MEDIUM 67
cost 25duplication 20delay 18 | |
| 15 | C/o Mahilasangam Building at Lothunur (v) Gollapalli (m) Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 16 | B/w Community Hall Near Sai baba Temple at Dharmapuri (v) in Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 17 | C/o Mudiraj Community hall at Shakapur (v) in Jagitial dist Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 18 | C/o Rajaka Sangam Community Hall at Keesulathapally (v) Pega Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 19 | C/o Mudiraj Sangam Community Hall at Keesulatapally (v) Pega Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 20 | C/o Gowda Sangam Community Hall at Rayapatnam (v) Dharmapuri Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 21 | C/o Mahilasangam Building at Lothunur (v) Gollapalli (m) Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 22 | B/w Community Hall Near Sai baba Temple at Dharmapuri (v) in Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 23 | C/o Mudiraj Community hall at Shakapur (v) in Jagitial dist Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 24 | C/o Rajaka Sangam Community Hall at Keesulathapally (v) Pega Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 25 | C/o Mudiraj Sangam Community Hall at Keesulatapally (v) Pega Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (67% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹5.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |