| 1 | Construction work of Kannada Sahitya Bhavan Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 373 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 2 | MARUTI SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 191 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 3 | Construction work of Kannada Sahitya Bhavan Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 373 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HAVERI | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 4 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 147 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹10.00 L | HIGH 73
cost 25delay 20duplication 20 | |
| 5 | construction of building for culture activities near Gramade Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
Read more (1 more)Show less- 97% similarity with another nearby work
| HAVERI | ₹10.00 L | MEDIUM 66
cost 25delay 25duplication 10 | |
| 6 | construction of building for culture activities near Gramade Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
Read more (1 more)Show less- 97% similarity with another nearby work
| HAVERI | ₹10.00 L | MEDIUM 66
cost 25delay 25duplication 10 | |
| 7 | Construction of Zilla Shahithya Bhavana Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 323 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 8 | |
| 8 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 208 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 60
delay 25duplication 20agency 8 | |
| 9 | BASAVESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 190 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 59
delay 25duplication 20agency 8 | |
| 10 | MARUTI SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 190 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 59
delay 25duplication 20agency 8 | |
| 11 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 191 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹5.00 L | MEDIUM 59
delay 25duplication 20agency 8 | |
| 12 | Construction of Zilla Shahithya Bhavana Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 323 days beyond expected completion
- 100% similarity with another nearby work
| HAVERI | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 13 | continuation of construction work of community hall in Haver Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 562 days beyond expected completion
- 100% similarity with another nearby work
| HAVERI | ₹5.00 L | MEDIUM 58
delay 25duplication 20cost 8 | |
| 14 | MARUTI SABHA BHAVAN Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - 157 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹50,000 | MEDIUM 58
delay 22duplication 20cost 8 | |
| 15 | Construction of Maremma Cultural bhavan at Neerlgudda villag Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in HAVERI (200% above, 155 peer works)
- 430 days beyond expected completion
Read more (1 more)Show less- 56% of this agency's ₹59,687,756 spend went to one vendor (Bommai Zilla Nirmithi Kendra), across 23 vendors and 185 transactions
| HAVERI | ₹15.00 L | MEDIUM 58 | |
| 16 | Construction of concreate around Shri Mukteshwara sabha Bhav Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 559 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 17 | Installing drinking water plants in Harijan keri in Agadi Vi Water — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹500,000 against a ₹199,475 median for Water works in HAVERI (151% above, 21 peer works)
- 559 days beyond expected completion
| HAVERI | ₹5.00 L | MEDIUM 55 | |
| 18 | construction of building for culture activities near Kuntayy Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 19 | construction of building for culture activities near Hondad Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 20 | construction of building for culture activities near Gramade Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 21 | construction of building for culture activities near Mailara Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 22 | construction of building for culture activities near Bhavan Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 23 | construction of bus sheds at property no-01 of konanakeri vi Community Buildings — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAVERI (100% above, 155 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 24 | construction of building for culture activities near Mailara Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |
| 25 | construction of building for culture activities near Dundi B Religious & Cultural — HAVERI(DEPUTY COMMISSIONER HAVERI_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in HAVERI (100% above, 27 peer works)
- 580 days beyond expected completion
| HAVERI | ₹10.00 L | MEDIUM 55 | |